Assessment Year | 2024 |
---|---|
Principal Product | Accordion Doors |
NAICS | 321911: Wood Window and Door Manufacturing |
SIC | 2431: Millwork |
Sales Range | $10 M to 50M |
# of Employees | 45 |
Plant Area |
170,000
ft2
|
Annual Production | 47
thousand feet
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $22,853 | 439,912 |
kWh
|
$0.052 | |
Electricity Demand | $22,612 | 3,106 |
kW-mo/yr
|
$7.28 | |
Electricity Fees | $7,345 | - |
|
- | |
Natural Gas | $39,951 | 4,426 |
MMBtu
|
$9.03 | |
LPG | $2,721 | 72 |
MMBtu
|
$37.79 | |
Other Gas | $3,652 | 1 |
MMBtu
|
$3,652.00 | |
Waste Disposal Costs | |||||
Water Usage | $68 | 22 |
Tgal
|
$3.06 | |
Other Liquid (non-haz) | $5,708 | 1 |
gal
|
$5,708.00 | |
TOTAL YEARLY COSTS | $104,910 | ||||
RECOMMENDED SAVINGS* | $1,219,314 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $323 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.111: Add equipment/ operators to reduce production bottleneck | $1,209,151 | $28,500 | - | - | - | - | $1,209,151 | |
02 | 2.7261: Install timers and/or thermostats | $4,224 | $1,583 | - | - | - |
$4,224
-
MMBtu
|
- | |
03 | 2.3212: Optimize plant power factor | $3,141 | $4,510 | - | - | $3,141 | - | - | |
04 | 2.4131: Size electric motors for peak operating efficiency | $2,475 | $16,140 |
$1,357
26,112
kWh
|
$1,118
-
kW-mo/yr
|
- | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $323 | - |
$149
2,871
kWh
|
$174
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $1,219,314 | $50,733 |
$1,506
28,983
kWh
|
$1,292
-
kW-mo/yr
|
$3,141 |
$4,224
-
MMBtu
|
$1,209,151 | ||
TOTAL IMPLEMENTED | $323 | - |
$149
2,871
kWh
|
$174
-
kW-mo/yr
|
- | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs