| Assessment Year | 2022 |
|---|---|
| Principal Product | Electrical Switchgear |
| NAICS | 335313: Switchgear and Switchboard Apparatus Manufacturing |
| SIC | 3613: Switchgear and Switchboard Apparatus |
| Sales Range | $50 M to 100M |
| # of Employees | 92 |
| Plant Area |
90,000
ft2
|
| Annual Production | 480
units
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $43,209 | 480,462 |
kWh
|
$0.090 | |
| Electricity Demand | $12,317 | 1,493 |
kW-mo/yr
|
$8.25 | |
| Electricity Fees | $5,627 | - |
|
- | |
| Natural Gas | $9,140 | 954 |
MMBtu
|
$9.58 | |
| Waste Disposal Costs | |||||
| Water Usage | $2,543 | 422 |
Tgal
|
$6.03 | |
| Water Disposal | $5,743 | 422 |
Tgal
|
$13.61 | |
| TOTAL YEARLY COSTS | $78,579 | ||||
| RECOMMENDED SAVINGS* | $124,164 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $84,906 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.122: Develop standard procedures to improve internal yields | $73,790 | - | - | - | - | - | - | - | $73,790 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,116 | $120,000 |
$7,307
89,129
kWh
|
$2,498
-
kW-mo/yr
|
$485 | $826 | - | - | - | |
| 03 | 4.421: Modify current incentive program | $978 | - | - | - | - | - | - | $978 | - | |
| 04 | 4.231: Purchase equipment instead of leasing | $38,280 | $221,950 | - | - | - | - | $38,280 | - | - | |
| TOTAL RECOMMENDED | $124,164 | $341,950 |
$7,307
89,129
kWh
|
$2,498
-
kW-mo/yr
|
$485 | $826 | $38,280 | $978 | $73,790 | ||
| TOTAL IMPLEMENTED | $84,906 | $120,000 |
$7,307
89,129
kWh
|
$2,498
-
kW-mo/yr
|
$485 | $826 | - | - | $73,790 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs