ITAC Assessment: UD0832
ITAC logo
ITAC Assessment: UD0832
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Surfactants for detergent industry
NAICS 325613: Surface Active Agent Manufacturing
SIC 2843: Surface Active Agents, Finishing Agents, Sulfonated Oils, and Assistants
Sales Range $100
M
to 500
M
# of Employees 46
Plant Area 42,500
ft2
Annual Production 250,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $827,197 12,228,127
kWh
Electricity Demand $107,992 1,742
kW-mo/yr
Natural Gas $375,466 39,988
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $149,602 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $86,370

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $14,751 $40,000 $13,247
210,269
kWh
$1,568
-
kW-mo/yr
- $(-64.0) -
02 2.7122: Disconnect ballasts $2,570 $250 $2,461
39,060
kWh
$291
-
kW-mo/yr
- $(-182.0) -
03 2.7135: Install occupancy sensors $1,977 $1,063 $1,707
27,099
kWh
- - $270 -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $56,419 $39,141 $39,009
849,863
kWh
$17,410
-
kW-mo/yr
- - -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,473 $16,265 $8,470
13,440
kWh
$1,003
-
kW-mo/yr
- - -
06 2.4321: Upgrade obsolete equipment $4,243 $4,728 $2,762
380,328
kWh
$1,481
-
kW-mo/yr
- - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $986 $500 $882
13,995
kWh
$104
-
kW-mo/yr
- - -
08 3.4156: Use flow control valves on equipment to optimize water use $5,424 $500 - - - - $5,424
-
Tgal
09 2.2437: Recover waste heat from equipment $25,624 $5,000 - - $25,624
-
MMBtu
- -
10 2.2113: Repair or replace steam traps $14,246 $2,000 - - $14,246
-
MMBtu
- -
11 2.1233: Analyze flue gas for proper air/fuel ratio $11,335 $2,620 - - $11,335
-
MMBtu
- -
12 2.2437: Recover waste heat from equipment $2,554 $5,000 - - $2,554
-
MMBtu
- -
TOTAL RECOMMENDED $149,602 $117,067 $68,538
1,534,054
kWh
$21,857
-
kW-mo/yr
$53,759
-
MMBtu
$24 $5,424
-
Tgal
TOTAL IMPLEMENTED $86,370 $86,182 $60,068
1,520,614
kWh
$20,854
-
kW-mo/yr
- $24 $5,424
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs