ITAC Assessment: OR0740
ITAC logo
ITAC Assessment: OR0740
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Treated Wastewater
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $10
M
to 50
M
# of Employees 13
Plant Area 921,270
ft2
Annual Production 1,000,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $244,496 4,322,411
kWh
Electricity Demand $42,369 15,017
kW-mo/yr
Electricity Fees $41,840 -
Natural Gas $35,870 5,550
MMBtu
TOTAL YEARLY COSTS $364,575
RECOMMENDED SAVINGS* $284,345 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $216,029

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.6231: Utilize controls to operate equipment only when needed $69,219 $8,189 $69,219
1,092,155
kWh
- -
02 2.4321: Upgrade obsolete equipment $68,316 $149,022 $61,424
969,440
kWh
$6,892
-
kW-mo/yr
-
03 2.4133: Use most efficient type of electric motors $54,988 $79,709 $42,558
671,677
kWh
$12,430
-
kW-mo/yr
-
04 2.4322: Use or replace with energy efficient substitutes $39,964 $60,439 $37,031
584,449
kWh
$2,933
-
kW-mo/yr
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $27,831 $84,560 $27,831
439,252
kWh
- -
06 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $14,480 $12,929 $14,480
228,535
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $9,547 $3,289 $6,012
94,888
kWh
$1,023
-
kW-mo/yr
$2,512
TOTAL RECOMMENDED $284,345 $398,137 $258,555
4,080,396
kWh
$23,278
-
kW-mo/yr
$2,512
TOTAL IMPLEMENTED $216,029 $249,115 $197,131
3,110,956
kWh
$16,386
-
kW-mo/yr
$2,512
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs