Assessment Year | 2002 |
---|---|
Principal Product | Building Face Brick |
NAICS |
n/a
|
SIC | 3251: Brick and Structural Clay Tile |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
166,250
ft2
|
Annual Production | 19,500,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $89,552 | 3,265,810 |
kWh
|
$0.027 |
Electricity Demand | $119,610 | 10,435 |
kW-mo/yr
|
$11.46 |
Natural Gas | $697,708 | 108,580 |
MMBtu
|
$6.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $103,244 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $98,492 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.652: Replace existing equipment with more suitable substitutes | $97,133 | $238,263 | - | - | $65,133 | $32,000 | |
02 | 2.4221: Install compressor air intakes in coolest locations | $883 | $2,000 |
$273
9,937
kWh
|
$610
-
kW-mo/yr
|
- | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,359 | - |
$488
17,659
kWh
|
$871
-
kW-mo/yr
|
- | - | |
04 | 2.4112: Install soft-start to eliminate nuisance trips | $3,869 | $7,000 | - |
$3,869
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $103,244 | $247,263 |
$761
27,596
kWh
|
$5,350
-
kW-mo/yr
|
$65,133 | $32,000 | ||
TOTAL IMPLEMENTED | $98,492 | $238,263 |
$488
17,659
kWh
|
$871
-
kW-mo/yr
|
$65,133 | $32,000 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs