Assessment Year | 2015 |
---|---|
Principal Product | Fruit Puree |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $50 M to 100M |
# of Employees | 110 |
Plant Area |
65,340
ft2
|
Annual Production | 6,500
Tgal
|
Production Hrs. Annual | 6,336
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $341,410 | 6,027,628 |
kWh
|
$0.057 |
Electricity Demand | $171,292 | 19,206 |
kW-mo/yr
|
$8.92 |
Electricity Fees | $46,188 | - |
|
- |
Natural Gas | $734,781 | 154,885 |
MMBtu
|
$4.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $165,350 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2121: Increase amount of condensate returned | $118,419 | $40,792 | - | - |
$46,488
-
MMBtu
|
$19,340
-
gal
|
$52,591
-
Tgal
|
|
02 | 2.2127: Flash condensate to produce lower pressure steam | $36,536 | $30,728 | - | - |
$36,536
-
MMBtu
|
- | - | |
03 | 2.2515: Use optimum thickness insulation | $3,897 | $4,580 | - | - |
$3,897
-
MMBtu
|
- | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $611 | $1,058 |
$611
10,562
kWh
|
- | - | - | - | |
05 | 2.2621: Modify refrigeration system to operate at a lower pressure | $4,262 | $15,398 |
$2,915
50,409
kWh
|
$1,347
-
kW-mo/yr
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,625 | $1,000 |
$1,606
29,373
kWh
|
$19
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $165,350 | $93,556 |
$5,132
90,344
kWh
|
$1,366
-
kW-mo/yr
|
$86,921
-
MMBtu
|
$19,340
-
gal
|
$52,591
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs