| Assessment Year | 2014 |
|---|---|
| Principal Product | Engineered Wood Facility |
| NAICS | 321213: Engineered Wood Member (except Truss) Manufacturing |
| SIC | 2439: Structural Wood Members, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 152 |
| Plant Area |
625,707
ft2
|
| Annual Production | 35,000
thousand feet
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $945,840 | 19,684,800 |
kWh
|
$0.048 |
| Electricity Demand | $379,801 | 44,281 |
kW-mo/yr
|
$8.58 |
| Electricity Fees | $55,815 | - |
|
- |
| Natural Gas | $1,439,531 | 296,787 |
MMBtu
|
$4.85 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $44,615 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $30,515 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1116: Improve combustion control capability | $14,677 | $12,315 |
$414
8,357
kWh
|
- | - |
$14,263
-
MMBtu
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,461 | $360 |
$5,567
112,478
kWh
|
- | - | - | $1,822 | $1,072 | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $10,572 | $7,500 | - |
$10,572
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.2511: Insulate bare equipment | $7,377 | $7,643 | - | - | - |
$7,377
-
MMBtu
|
- | - | |
| 05 | 2.3212: Optimize plant power factor | $3,528 | $15,201 | - | - | $3,528 | - | - | - | |
| TOTAL RECOMMENDED | $44,615 | $43,019 |
$5,981
120,835
kWh
|
$10,572
-
kW-mo/yr
|
$3,528 |
$21,640
-
MMBtu
|
$1,822 | $1,072 | ||
| TOTAL IMPLEMENTED | $30,515 | $20,318 |
$5,981
120,835
kWh
|
- | - |
$21,640
-
MMBtu
|
$1,822 | $1,072 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs