ITAC Assessment: OR0639
ITAC logo
ITAC Assessment: OR0639
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Engineered Wood Facility
NAICS 321213: Engineered Wood Member (except Truss) Manufacturing
SIC 2439: Structural Wood Members, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 152
Plant Area 625,707
ft2
Annual Production 35,000
thousand feet
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $945,840 19,684,800
kWh
Electricity Demand $379,801 44,281
kW-mo/yr
Electricity Fees $55,815 -
Natural Gas $1,439,531 296,787
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,615 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,515

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.1116: Improve combustion control capability $14,677 $12,315 $414
8,357
kWh
- - $14,263
-
MMBtu
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $8,461 $360 $5,567
112,478
kWh
- - - $1,822 $1,072
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $10,572 $7,500 - $10,572
-
kW-mo/yr
- - - -
04 2.2511: Insulate bare equipment $7,377 $7,643 - - - $7,377
-
MMBtu
- -
05 2.3212: Optimize plant power factor $3,528 $15,201 - - $3,528 - - -
TOTAL RECOMMENDED $44,615 $43,019 $5,981
120,835
kWh
$10,572
-
kW-mo/yr
$3,528 $21,640
-
MMBtu
$1,822 $1,072
TOTAL IMPLEMENTED $30,515 $20,318 $5,981
120,835
kWh
- - $21,640
-
MMBtu
$1,822 $1,072
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs