Assessment Year | 2014 |
---|---|
Principal Product | Plywood and LVL |
NAICS | 321212: Softwood Veneer and Plywood Manufacturing |
SIC | 2436: Softwood Veneer and Plywood |
Sales Range | $50 M to 100M |
# of Employees | 317 |
Plant Area |
450,000
ft2
|
Annual Production | 120,000,000
units
|
Production Hrs. Annual | 4,992
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,128,644 | 21,416,400 |
kWh
|
$0.053 |
Electricity Demand | $294,462 | 40,898 |
kW-mo/yr
|
$7.20 |
Electricity Fees | $2,520 | - |
|
- |
LPG | $173,372 | 9,592 |
MMBtu
|
$18.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $352,579 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $29,475 | $7,174 |
$29,475
561,751
kWh
|
- | - | - | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,287 | $1,628 |
$6,287
119,816
kWh
|
- | - | - | - | |
03 | 2.2121: Increase amount of condensate returned | $56,191 | $56,191 | - | - | - | - |
$56,191
-
Tgal
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,844 | $15,843 |
$12,337
234,090
kWh
|
$2,507
-
kW-mo/yr
|
- | - | - | |
05 | 4.652: Replace existing equipment with more suitable substitutes | $23,961 | $9,068 |
$23,961
454,665
kWh
|
- | - | - | - | |
06 | 2.7144: Install spectral reflectors / delamp | $181,002 | $170,561 |
$130,333
2,473,114
kWh
|
$17,393
-
kW-mo/yr
|
$3,381 | $29,895 | - | |
07 | 2.4224: Upgrade controls on compressors | $40,819 | $43,800 |
$45,531
863,970
kWh
|
$(-4,712.0)
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $352,579 | $304,265 |
$247,924
4,707,406
kWh
|
$15,188
-
kW-mo/yr
|
$3,381 | $29,895 |
$56,191
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs