ITAC Assessment: OR0606
ITAC logo
ITAC Assessment: OR0606
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Reclaimed Water
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 150
Plant Area 2,000,000
ft2
Annual Production 41,975,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $3,714,428 65,253,760
kWh
Electricity Demand $485,134 131,102
kW-mo/yr
Natural Gas $104,241 10,686
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $364,015 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.4224: Upgrade controls on compressors $161,379 $344 $161,379
2,662,577
kWh
- -
02 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $39,128 - $36,108
595,743
kWh
$3,020
-
kW-mo/yr
-
03 2.6218: Turn off equipment when not in use $119,795 - $89,199
1,471,680
kWh
$7,963
-
kW-mo/yr
$22,633
04 4.632: Change operating conditions $14,380 - $13,201
217,810
kWh
$1,179
-
kW-mo/yr
-
05 2.5123: Reduce fluid flow rates $9,051 $9,200 $8,083
133,376
kWh
$968
-
kW-mo/yr
-
06 2.6218: Turn off equipment when not in use $20,282 $25,500 $20,282
334,632
kWh
- -
TOTAL RECOMMENDED $364,015 $35,044 $328,252
5,415,818
kWh
$13,130
-
kW-mo/yr
$22,633
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs