Assessment Year | 2013 |
---|---|
Principal Product | Lumber |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $5 M to 10M |
# of Employees | 65 |
Plant Area |
4,500
ft2
|
Annual Production | 25,000
thousand feet
|
Production Hrs. Annual | 4,060
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $149,576 | 2,733,197 |
kWh
|
$0.055 |
Electricity Demand | $72,760 | 9,571 |
kW-mo/yr
|
$7.60 |
Electricity Fees | $17,389 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $249,195 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $224,987 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.122: Develop standard procedures to improve internal yields | $199,441 | $59,312 |
$4,369
79,184
kWh
|
- | - | - | - | $195,072 | |
02 | 4.463: Modify facility to avoid excess maintenance costs | $17,131 | $45,000 |
$(-998.0)
(-18,094)
kWh
|
$(-2,298.0)
-
kW-mo/yr
|
- | $18,631 | $1,796 | - | |
03 | 2.4224: Upgrade controls on compressors | $14,855 | $19,467 |
$14,420
261,334
kWh
|
$435
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7135: Install occupancy sensors | $5,434 | $10,283 |
$3,520
63,794
kWh
|
$413
-
kW-mo/yr
|
- | $893 | $608 | - | |
05 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $4,904 | $4,472 |
$3,560
64,512
kWh
|
$1,344
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.3212: Optimize plant power factor | $3,822 | $9,150 | - | - | $3,822 | - | - | - | |
07 | 2.4322: Use or replace with energy efficient substitutes | $2,173 | $2,020 |
$1,232
22,320
kWh
|
$941
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,435 | $3,004 |
$977
17,713
kWh
|
$458
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $249,195 | $152,708 |
$27,080
490,763
kWh
|
$1,293
-
kW-mo/yr
|
$3,822 | $19,524 | $2,404 | $195,072 | ||
TOTAL IMPLEMENTED | $224,987 | $101,216 |
$23,286
422,025
kWh
|
$1,306
-
kW-mo/yr
|
$3,822 | $893 | $608 | $195,072 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs