ITAC Assessment: OR0602
ITAC logo
ITAC Assessment: OR0602
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Lumber
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $5
M
to 10
M
# of Employees 65
Plant Area 4,500
ft2
Annual Production 25,000
thousand feet
Production Hrs. Annual 4,060
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $149,576 2,733,197
kWh
Electricity Demand $72,760 9,571
kW-mo/yr
Electricity Fees $17,389 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $249,195 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $224,987

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 4.122: Develop standard procedures to improve internal yields $199,441 $59,312 $4,369
79,184
kWh
- - - - $195,072
02 4.463: Modify facility to avoid excess maintenance costs $17,131 $45,000 $(-998.0)
(-18,094)
kWh
$(-2,298.0)
-
kW-mo/yr
- $18,631 $1,796 -
03 2.4224: Upgrade controls on compressors $14,855 $19,467 $14,420
261,334
kWh
$435
-
kW-mo/yr
- - - -
04 2.7135: Install occupancy sensors $5,434 $10,283 $3,520
63,794
kWh
$413
-
kW-mo/yr
- $893 $608 -
05 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $4,904 $4,472 $3,560
64,512
kWh
$1,344
-
kW-mo/yr
- - - -
06 2.3212: Optimize plant power factor $3,822 $9,150 - - $3,822 - - -
07 2.4322: Use or replace with energy efficient substitutes $2,173 $2,020 $1,232
22,320
kWh
$941
-
kW-mo/yr
- - - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,435 $3,004 $977
17,713
kWh
$458
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $249,195 $152,708 $27,080
490,763
kWh
$1,293
-
kW-mo/yr
$3,822 $19,524 $2,404 $195,072
TOTAL IMPLEMENTED $224,987 $101,216 $23,286
422,025
kWh
$1,306
-
kW-mo/yr
$3,822 $893 $608 $195,072
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs