Assessment Year | 1998 |
---|---|
Principal Product | Livestock Feeds |
NAICS |
n/a
|
SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
Sales Range | $10 M to 50M |
# of Employees | 30 |
Plant Area |
80,000
ft2
|
Annual Production | 130,000
ton
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $99,089 | 3,472,743 |
kWh
|
$0.029 |
Electricity Demand | $98,441 | - |
|
- |
Electricity Fees | $6,064 | - |
|
- |
Natural Gas | $47,109 | 11,258 |
MMBtu
|
$4.18 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,457 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,124 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,871 | $1,728 |
$1,654
60,961
kWh
|
$1,217
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,968 | $1,477 |
$780
28,722
kWh
|
$574
-
kW-mo/yr
|
- | - | - | $614 | |
03 | 2.6232: Install set-back timers | $1,164 | $146 | - | - |
$1,164
-
MMBtu
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,020 | $400 |
$1,020
37,515
kWh
|
- | - | - | - | - | |
05 | 2.7135: Install occupancy sensors | $1,104 | $1,566 |
$1,104
37,808
kWh
|
- | - | - | - | - | |
06 | 4.652: Replace existing equipment with more suitable substitutes | $34,130 | $12,800 | - | - | - | - | $8,130 | $26,000 | |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,200 | $6,000 | - | - | - |
$2,200
-
lb
|
- | - | |
TOTAL RECOMMENDED | $44,457 | $24,117 |
$4,558
165,006
kWh
|
$1,791
-
kW-mo/yr
|
$1,164
-
MMBtu
|
$2,200
-
lb
|
$8,130 | $26,614 | ||
TOTAL IMPLEMENTED | $2,124 | $1,966 |
$2,124
75,323
kWh
|
- | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs