Assessment Year | 2012 |
---|---|
Principal Product | Steel |
NAICS | 331110: Iron and Steel Mills and Ferroalloy Manufacturing |
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $1 M to 5M |
# of Employees | 150 |
Plant Area |
40,000
ft2
|
Annual Production | 10,400,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $232,388 | 4,950,030 |
kWh
|
$0.047 |
Electricity Demand | $163,636 | 26,345 |
kW-mo/yr
|
$6.21 |
Electricity Fees | $24,072 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $440,700 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.5221: Recycle casting sand | $437,377 | $71,170 | - | - |
$20,000
-
lb
|
$417,377 | |
02 | 2.4224: Upgrade controls on compressors | $2,289 | $1,015 |
$1,089
23,197
kWh
|
$1,200
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,034 | $1,534 |
$617
13,142
kWh
|
$417
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $440,700 | $73,719 |
$1,706
36,339
kWh
|
$1,617
-
kW-mo/yr
|
$20,000
-
lb
|
$417,377 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs