| Assessment Year | 2012 |
|---|---|
| Principal Product | Windows and Doors |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 230 |
| Plant Area |
140,000
ft2
|
| Annual Production | 240,000,000
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $103,526 | 1,763,400 |
kWh
|
$0.059 |
| Electricity Demand | $43,851 | 6,705 |
kW-mo/yr
|
$6.54 |
| Electricity Fees | $11,469 | - |
|
- |
| Natural Gas | $11,918 | 1,199 |
MMBtu
|
$9.94 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $79,020 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,114 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4323: Use optimum size and capacity equipment | $8,836 | $7,417 |
$6,275
104,832
kWh
|
$2,561
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.6212: Turn off equipment during breaks, reduce operating time | $2,690 | $2,000 |
$2,690
44,941
kWh
|
- | - | - | - | |
| 03 | 2.7261: Install timers and/or thermostats | $1,776 | $500 |
$1,776
29,676
kWh
|
- | - | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,028 | $2,305 |
$2,278
37,968
kWh
|
$750
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,171 | $1,000 |
$2,371
39,520
kWh
|
$800
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.2437: Recover waste heat from equipment | $1,942 | $1,000 | - | - |
$1,942
-
MMBtu
|
- | - | |
| 07 | 2.7135: Install occupancy sensors | $13,449 | $24,282 |
$9,633
160,956
kWh
|
$1,371
-
kW-mo/yr
|
- | $1,873 | $572 | |
| 08 | 3.1191: Change procedures / equipment / operating conditions | $16,379 | $16,379 |
$10,423
174,153
kWh
|
$5,956
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.9114: Use solar heat to make electricty | $7,083 | $47,838 |
$6,660
111,277
kWh
|
$423
-
kW-mo/yr
|
- | - | - | |
| 10 | 4.131: Modify process to reduce material use/cost | $8,580 | - | - | - | - | - | $8,580 | |
| 11 | 2.4131: Size electric motors for peak operating efficiency | $12,086 | $16,390 |
$11,219
170,808
kWh
|
$867
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $79,020 | $119,111 |
$53,325
874,131
kWh
|
$12,728
-
kW-mo/yr
|
$1,942
-
MMBtu
|
$1,873 | $9,152 | ||
| TOTAL IMPLEMENTED | $15,114 | $18,695 |
$13,497
208,776
kWh
|
$1,617
-
kW-mo/yr
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs