ITAC Assessment: OR0578
ITAC logo
ITAC Assessment: OR0578
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Aircraft components
NAICS 333517: Machine Tool Manufacturing
SIC 3365: Aluminum Foundries
Sales Range $50
M
to 100
M
# of Employees 260
Plant Area 150,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,240
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $312,497 4,470,644
kWh
Electricity Demand $60,302 12,914
kW-mo/yr
Electricity Fees $20,248 -
Natural Gas $206,572 23,936
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $110,665 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $62,544

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.2443: Re-use or recycle hot or cold process exhaust air $3,007 $5,720 - - - $3,007
-
MMBtu
- -
02 2.8112: Combine utility meters $30,616 - - - $30,616 - - -
03 2.7261: Install timers and/or thermostats $10,803 $3,800 - - - $10,803
-
MMBtu
- -
04 2.7134: Use photocell controls $28,921 $21,150 $23,196
262,076
kWh
- - - $3,151 $2,574
05 2.7491: Insulate glazing, walls, ceilings, and roofs $10,360 $13,329 - - - $10,360
-
MMBtu
- -
06 2.4133: Use most efficient type of electric motors $26,958 $97,580 $21,609
318,144
kWh
$5,349
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $110,665 $141,579 $44,805
580,220
kWh
$5,349
-
kW-mo/yr
$30,616 $24,170
-
MMBtu
$3,151 $2,574
TOTAL IMPLEMENTED $62,544 $26,870 $23,196
262,076
kWh
- $30,616 $3,007
-
MMBtu
$3,151 $2,574
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs