Assessment Year | 2009 |
---|---|
Principal Product | Dimensional Lumber, Specialty order Lumber and Beams |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
100,000
ft2
|
Annual Production | 20,000
thousand feet
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $129,750 | 3,074,720 |
kWh
|
$0.042 |
Electricity Demand | $72,095 | 15,943 |
kW-mo/yr
|
$4.52 |
Electricity Fees | $29,714 | - |
|
- |
Wood | $195,000 | 171,600 |
MMBtu
|
$1.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $167,848 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $77,108 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Wood Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1336: Install equipment to utilize waste fuel | $90,740 | $81,950 | - | - | - |
$90,740
-
MMBtu
|
|
02 | 2.1232: Keep boiler tubes clean | $39,218 | $44,000 | - | - | - |
$39,218
-
MMBtu
|
|
03 | 2.2136: Install / repair insulation on steam lines | $939 | $1,042 | - | - | - |
$939
-
MMBtu
|
|
04 | 2.4323: Use optimum size and capacity equipment | $705 | - |
$705
16,000
kWh
|
- | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $5,091 | $5,000 |
$3,305
75,000
kWh
|
$1,786
-
kW-mo/yr
|
- | - | |
06 | 2.4224: Upgrade controls on compressors | $16,829 | $20,313 |
$11,943
271,853
kWh
|
$4,886
-
kW-mo/yr
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,257 | $500 |
$3,627
85,000
kWh
|
$630
-
kW-mo/yr
|
- | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,090 | $500 |
$1,090
22,815
kWh
|
- | - | - | |
09 | 2.8112: Combine utility meters | $6,709 | - | - | - | $6,709 | - | |
10 | 2.4133: Use most efficient type of electric motors | $2,270 | $15,676 |
$2,270
33,072
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $167,848 | $168,981 |
$22,940
503,740
kWh
|
$7,302
-
kW-mo/yr
|
$6,709 |
$130,897
-
MMBtu
|
||
TOTAL IMPLEMENTED | $77,108 | $87,031 |
$22,940
503,740
kWh
|
$7,302
-
kW-mo/yr
|
$6,709 |
$40,157
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Wood Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs