| Assessment Year | 2024 |
|---|---|
| Principal Product | Wastewater Treatment |
| NAICS | 325612: Polish and Other Sanitation Good Manufacturing |
| SIC | 2842: Specialty Cleaning, Polishing, and Sanitation Preparations |
| Sales Range | $100 M to 500M |
| # of Employees | 156 |
| Plant Area |
871,200
ft2
|
| Annual Production | 7,300,000
Tgal
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,736,126 | 27,919,500 |
kWh
|
$0.062 |
| Electricity Demand | $536,909 | 49,044 |
kW-mo/yr
|
$10.95 |
| Natural Gas | $421,221 | 140,405 |
MMBtu
|
$3.00 |
| TOTAL YEARLY COSTS | $2,694,256 | |||
| RECOMMENDED SAVINGS* | $1,138,447 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,075,803 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $2,180 | $250 |
$2,180
34,596
kWh
|
- | - | |
| 02 | 2.4226: Use / purchase optimum sized compressor | $265,645 | $63,000 |
$265,645
4,284,573
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,889 | $1,050 |
$1,517
24,460
kWh
|
$372
-
kW-mo/yr
|
- | |
| 04 | 2.2622: Replace existing chiller with high efficiency model | $810,158 | $2,364,120 |
$810,158
13,067,059
kWh
|
- | - | |
| 05 | 2.1224: Replace boiler | $58,575 | $420,000 | - | - |
$58,575
-
MMBtu
|
|
| TOTAL RECOMMENDED | $1,138,447 | $2,848,420 |
$1,079,500
17,410,688
kWh
|
$372
-
kW-mo/yr
|
$58,575
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $1,075,803 | $2,427,120 |
$1,075,803
17,351,632
kWh
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs