ITAC Assessment: LS2414
ITAC logo
ITAC Assessment: LS2414
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Wastewater Treatment
NAICS 325612: Polish and Other Sanitation Good Manufacturing
SIC 2842: Specialty Cleaning, Polishing, and Sanitation Preparations
Sales Range $100
M
to 500
M
# of Employees 156
Plant Area 871,200
ft2
Annual Production 7,300,000
Tgal
Production Hrs. Annual 8,736
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,736,126 27,919,500
kWh
Electricity Demand $536,909 49,044
kW-mo/yr
Natural Gas $421,221 140,405
MMBtu
TOTAL YEARLY COSTS $2,694,256
RECOMMENDED SAVINGS* $1,138,447 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7135: Install occupancy sensors $2,180 $250 $2,180
34,596
kWh
- -
02 2.4226: Use / purchase optimum sized compressor $265,645 $63,000 $265,645
4,284,573
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,889 $1,050 $1,517
24,460
kWh
$372
-
kW-mo/yr
-
04 2.2622: Replace existing chiller with high efficiency model $810,158 $2,364,120 $810,158
13,067,059
kWh
- -
05 2.1224: Replace boiler $58,575 $420,000 - - $58,575
-
MMBtu
TOTAL RECOMMENDED $1,138,447 $2,848,420 $1,079,500
17,410,688
kWh
$372
-
kW-mo/yr
$58,575
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs