Assessment Year | 2008 |
---|---|
Principal Product | French Fries |
NAICS | 311423: Dried and Dehydrated Food Manufacturing |
SIC | 3556: Food Products Machinery |
Sales Range | $100 M to 500M |
# of Employees | 400 |
Plant Area |
130,000
ft2
|
Annual Production | 401,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,235,732 | 55,604,138 |
kWh
|
$0.040 |
Electricity Demand | $293,491 | 96,613 |
kW-mo/yr
|
$3.04 |
Electricity Fees | $82,793 | - |
|
- |
Natural Gas | $5,471,680 | 789,216 |
MMBtu
|
$6.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $611,768 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $341,220 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2711: Utilize outside air instead of conditioned air for drying | $244,531 | $29,019 | - |
$244,531
-
MMBtu
|
- | - | |
02 | 2.2437: Recover waste heat from equipment | $61,542 | $40,950 | - |
$61,542
-
MMBtu
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $26,017 | $28,000 |
$26,017
596,160
kWh
|
- | - | - | |
04 | 2.2136: Install / repair insulation on steam lines | $2,107 | $413 | - |
$2,107
-
MMBtu
|
- | - | |
05 | 2.7135: Install occupancy sensors | $19,521 | $31,119 |
$19,521
1,230
kWh
|
- | - | - | |
06 | 2.3212: Optimize plant power factor | $10,290 | $54,000 | - | - | - | $10,290 | |
07 | 2.4133: Use most efficient type of electric motors | $42,310 | $148,560 |
$42,310
3,017
kWh
|
- | - | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,510 | - |
$8,510
607
kWh
|
- | - | - | |
09 | 2.2621: Modify refrigeration system to operate at a lower pressure | $78,900 | $132,800 |
$78,900
6,169
kWh
|
- | - | - | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,500 | $43,600 |
$11,500
899
kWh
|
- | - | - | |
11 | 3.1191: Change procedures / equipment / operating conditions | $52,540 | $2,200 | - | - | $52,540 | - | |
12 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $46,700 | $46,700 |
$46,700
3,400
kWh
|
- | - | - | |
13 | 2.4224: Upgrade controls on compressors | $7,300 | $5,700 |
$7,300
535
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $611,768 | $563,061 |
$240,758
612,017
kWh
|
$308,180
-
MMBtu
|
$52,540 | $10,290 | ||
TOTAL IMPLEMENTED | $341,220 | $506,042 |
$214,741
15,857
kWh
|
$63,649
-
MMBtu
|
$52,540 | $10,290 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs