Assessment Year | 2008 |
---|---|
Principal Product | High Voltage Cable |
NAICS | 331318: Other Aluminum Rolling, Drawing, and Extruding |
SIC | 3357: Drawing and Insulating of Nonferrous Wire |
Sales Range | $100 M to 500M |
# of Employees | 50 |
Plant Area |
250,000
ft2
|
Annual Production | 146,800
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $397,579 | 10,233,686 |
kWh
|
$0.039 |
Electricity Demand | $69,786 | 24,064 |
kW-mo/yr
|
$2.90 |
Electricity Fees | $65,425 | - |
|
- |
Natural Gas | $118,265 | 127,756 |
MMBtu
|
$0.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $664,990 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.111: Add equipment/ operators to reduce production bottleneck | $218,543 | $1,128,211 |
$113,514
9,964
kWh
|
$(-9,061.0)
-
kW-mo/yr
|
- | $114,090 | - | - | |
02 | 2.3322: Use existing dam to generate electricity | $31,589 | $50,000 | - | - | $31,589 | - | - | - | |
03 | 2.7135: Install occupancy sensors | $5,432 | $23,075 |
$2,918
75,130
kWh
|
$98
-
kW-mo/yr
|
- | $645 | - | $1,771 | |
04 | 2.9114: Use solar heat to make electricty | $106,649 | $758,330 |
$96,766
2,490,750
kWh
|
$9,883
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $15,317 | $72,600 |
$12,157
312,920
kWh
|
$3,160
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.3212: Optimize plant power factor | $4,450 | $19,950 | - | - | $4,450 | - | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,860 | - |
$1,589
140
kWh
|
$271
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,510 | - |
$748
177,869
kWh
|
$7,762
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.2621: Modify refrigeration system to operate at a lower pressure | $78,900 | $132,800 |
$78,900
1,998,900
kWh
|
- | - | - | - | - | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $87,200 | $43,600 |
$87,200
263,600
kWh
|
- | - | - | - | - | |
11 | 3.2111: Install redundant equipment to avoid losses caused by equipment failure and routine maintenance | $52,540 | $2,200 | - | - | - | - | $52,540 | - | |
12 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $46,700 | $46,700 |
$43,500
997,000
kWh
|
$3,200
-
kW-mo/yr
|
- | - | - | - | |
13 | 2.4224: Upgrade controls on compressors | $7,300 | $5,700 |
$6,900
157,000
kWh
|
$400
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $664,990 | $2,283,166 |
$444,192
6,483,273
kWh
|
$15,713
-
kW-mo/yr
|
$36,039 | $114,735 | $52,540 | $1,771 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs