Assessment Year | 1999 |
---|---|
Principal Product | reinforced rubber hose |
NAICS |
n/a
|
SIC | 3052: Rubber and Plastics Hose and Belting |
Sales Range | $10 M to 50M |
# of Employees | 230 |
Plant Area |
250,000
ft2
|
Annual Production | 12,000
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $432,757 | 23,342,028 |
kWh
|
$0.019 |
Electricity Demand | $699,969 | 49,608 |
kW-mo/yr
|
$14.11 |
Natural Gas | $93,885 | 21,690 |
MMBtu
|
$4.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $270,112 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $74,578 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.5218: Reuse / recycle/ sell rubber products | $110,878 | $86,000 |
$(-566.0)
(-26,964)
kWh
|
$(-5,486.0)
-
kW-mo/yr
|
- |
$44,730
-
lb
|
- | - | - | $72,200 | |
02 | 3.4111: Use closed cycle process to minimize waste water production | $59,980 | $6,380 | - | - |
$59,980
-
Tgal
|
- | - | - | - | - | |
03 | 2.3134: Shift from daytime to nighttime operation | $53,332 | - | - |
$60,820
-
kW-mo/yr
|
- | - | $(-7,488.0) | - | - | - | |
04 | 4.322: Eliminate old stock and modify inventory control | $19,000 | - | - | - | - | - | - | - | $19,000 | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $14,598 | $15,000 |
$6,369
303,341
kWh
|
$8,229
-
kW-mo/yr
|
- | - | - | - | - | - | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $10,800 | - | - | - | - | - | - | $10,800 | - | - | |
07 | 2.3132: Recharge batteries on during off-peak demand periods | $1,524 | - | - |
$1,524
-
kW-mo/yr
|
- | - | - | - | - | - | |
TOTAL RECOMMENDED | $270,112 | $107,380 |
$5,803
276,377
kWh
|
$65,087
-
kW-mo/yr
|
$59,980
-
Tgal
|
$44,730
-
lb
|
$(-7,488.0) | $10,800 | $19,000 | $72,200 | ||
TOTAL IMPLEMENTED | $74,578 | $21,380 |
$6,369
303,341
kWh
|
$8,229
-
kW-mo/yr
|
$59,980
-
Tgal
|
- | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs