Assessment Year | 2006 |
---|---|
Principal Product | Fibercement siding |
NAICS | 327390: Other Concrete Product Manufacturing |
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $50 M to 100M |
# of Employees | 88 |
Plant Area |
145,000
ft2
|
Annual Production | 120,000
thousand feet
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $688,460 | 20,088,000 |
kWh
|
$0.034 |
Electricity Demand | $161,872 | 3,190 |
kW-mo/yr
|
$50.74 |
Electricity Fees | $36,412 | - |
|
- |
Natural Gas | $1,313,458 | 125,047 |
MMBtu
|
$10.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $230,500 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $109,800 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $64,300 | $20,000 | - | - |
$64,300
-
MMBtu
|
- | |
02 | 2.1394: Replace steam jets on vacuum system with electric motor driven vacuum pumps | $22,500 | $44,500 |
$(-3,400.0)
(-95,400)
kWh
|
$(-1,400.0)
-
kW-mo/yr
|
$27,300
-
MMBtu
|
- | |
03 | 3.6192: Use a less expensive method of waste removal | $84,100 | - | - | - | - | $84,100 | |
04 | 3.6192: Use a less expensive method of waste removal | $28,000 | - | - | - | - | $28,000 | |
05 | 2.6242: Minimize operation of equipment maintained in standby condition | $23,000 | - |
$23,000
650,800
kWh
|
- | - | - | |
06 | 2.5194: Redesign process | $6,100 | $5,000 |
$5,200
152,400
kWh
|
$900
-
kW-mo/yr
|
- | - | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $2,500 | $1,000 |
$2,500
70,000
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $230,500 | $70,500 |
$27,300
777,800
kWh
|
$(-500.0)
-
kW-mo/yr
|
$91,600
-
MMBtu
|
$112,100 | ||
TOTAL IMPLEMENTED | $109,800 | $64,500 |
$19,600
555,400
kWh
|
$(-1,400.0)
-
kW-mo/yr
|
$91,600
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs