Assessment Year | 2005 |
---|---|
Principal Product | Laundry Equipment |
NAICS | 333318: Other Commercial and Service Industry Machinery Manufacturing |
SIC | 3582: Commercial Laundry, Drycleaning, and Pressing Machines |
Sales Range | $1 M to 5M |
# of Employees | 36 |
Plant Area |
50,000
ft2
|
Annual Production | 80
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $40,433 | 734,080 |
kWh
|
$0.055 |
Electricity Demand | $10,254 | 3,347 |
kW-mo/yr
|
$3.06 |
Electricity Fees | $2,861 | - |
|
- |
Natural Gas | $32,976 | 3,759 |
MMBtu
|
$8.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,950 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,200 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2514: Cover open tanks | $7,300 | $3,600 |
$7,300
132,000
kWh
|
- | - | - | |
02 | 2.1113: Reduce combustion air flow to optimum | $1,300 | - | - | - |
$1,300
-
MMBtu
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,300 | $2,300 |
$1,800
32,000
kWh
|
$500
-
kW-mo/yr
|
- | - | |
04 | 2.4224: Upgrade controls on compressors | $1,450 | $1,800 |
$1,250
22,900
kWh
|
$200
-
kW-mo/yr
|
- | - | |
05 | 2.1231: Establish burner maintenance schedule for boilers | $600 | $400 | - | - |
$600
-
MMBtu
|
- | |
06 | 2.4226: Use / purchase optimum sized compressor | $5,400 | $20,000 |
$4,300
78,000
kWh
|
$1,100
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,600 | $17,400 |
$2,850
51,740
kWh
|
$650
-
kW-mo/yr
|
- | $100 | |
TOTAL RECOMMENDED | $21,950 | $45,500 |
$17,500
316,640
kWh
|
$2,450
-
kW-mo/yr
|
$1,900
-
MMBtu
|
$100 | ||
TOTAL IMPLEMENTED | $19,200 | $43,700 |
$16,250
293,740
kWh
|
$2,250
-
kW-mo/yr
|
$600
-
MMBtu
|
$100 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs