Assessment Year | 2005 |
---|---|
Principal Product | Lumber |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $50 M to 100M |
# of Employees | 163 |
Plant Area |
2,178,000
ft2
|
Annual Production | 88,771,919
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $712,741 | 18,643,489 |
kWh
|
$0.038 |
Electricity Demand | $114,766 | 41,353 |
kW-mo/yr
|
$2.78 |
Electricity Fees | $20,992 | - |
|
- |
Natural Gas | $351,475 | 50,057 |
MMBtu
|
$7.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,378,500 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $66,800 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.131: Modify process to reduce material use/cost | $249,000 | $15,000 | - | - | - | - | $(-432,000.0) | $681,000 | - | - | |
02 | 4.125: | $379,000 | $168,000 | - | - | - | - | - | - | - | $379,000 | |
03 | 2.4322: Use or replace with energy efficient substitutes | $15,400 | $6,000 |
$15,400
402,000
kWh
|
- | - | - | - | - | - | - | |
04 | 2.3212: Optimize plant power factor | $15,000 | $8,750 | - | - | $15,000 | - | - | - | - | - | |
05 | 2.1231: Establish burner maintenance schedule for boilers | $8,900 | $900 | - | - | - |
$9,800
-
MMBtu
|
$(-900.0) | - | - | - | |
06 | 2.7124: Make a practice of turning off lights when not needed | $5,800 | $1,500 |
$4,400
116,500
kWh
|
- | - | - | $1,400 | - | - | - | |
07 | 2.4224: Upgrade controls on compressors | $3,900 | $1,800 |
$4,100
110,000
kWh
|
$(-200.0)
-
kW-mo/yr
|
- | - | - | - | - | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $2,400 | $2,100 |
$2,300
60,000
kWh
|
$100
-
kW-mo/yr
|
- | - | - | - | - | - | |
09 | 2.7124: Make a practice of turning off lights when not needed | $13,300 | $13,100 |
$9,100
236,900
kWh
|
- | - | - | $400 | - | $3,800 | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,700 | $4,700 |
$4,100
110,000
kWh
|
$600
-
kW-mo/yr
|
- | - | - | - | - | - | |
11 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $32,700 | $52,000 |
$29,000
760,000
kWh
|
$3,700
-
kW-mo/yr
|
- | - | - | - | - | - | |
12 | 2.2437: Recover waste heat from equipment | $611,000 | $1,406,000 | - | - | - | - | - | - | $39,000 | $572,000 | |
13 | 2.4133: Use most efficient type of electric motors | $21,000 | $49,000 |
$19,000
504,000
kWh
|
$2,000
-
kW-mo/yr
|
- | - | - | - | - | - | |
14 | 2.4226: Use / purchase optimum sized compressor | $12,900 | $31,000 |
$12,200
316,900
kWh
|
$700
-
kW-mo/yr
|
- | - | - | - | - | - | |
15 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,500 | $15,000 |
$2,710
70,800
kWh
|
$790
-
kW-mo/yr
|
- | - | - | - | - | - | |
TOTAL RECOMMENDED | $1,378,500 | $1,774,850 |
$102,310
2,687,100
kWh
|
$7,690
-
kW-mo/yr
|
$15,000 |
$9,800
-
MMBtu
|
$(-431,100.0) | $681,000 | $42,800 | $951,000 | ||
TOTAL IMPLEMENTED | $66,800 | $78,250 |
$36,300
960,900
kWh
|
$2,400
-
kW-mo/yr
|
$15,000 |
$9,800
-
MMBtu
|
$(-500.0) | - | $3,800 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs