Assessment Year | 2005 |
---|---|
Principal Product | stud and dimensioned lumber |
NAICS | 321219: Reconstituted Wood Product Manufacturing |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $50 M to 100M |
# of Employees | 230 |
Plant Area |
150,000
ft2
|
Annual Production | 135,000
thousand feet
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,677,620 | 37,812,096 |
kWh
|
$0.044 |
Electricity Demand | $303,169 | 70,178 |
kW-mo/yr
|
$4.32 |
Electricity Fees | $1,119 | - |
|
- |
Fuel Oil #6 | $215,630 | 32,714 |
MMBtu
|
$6.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $187,525 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Wood Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,420 | $6,500 |
$6,310
142,227
kWh
|
$110
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $19,180 | - |
$18,852
424,882
kWh
|
$328
-
kW-mo/yr
|
- | - | |
03 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $6,760 | $15,400 |
$6,685
150,600
kWh
|
$75
-
kW-mo/yr
|
- | - | |
04 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $64,700 | $19,500 | - | - | - |
$64,700
-
MMBtu
|
|
05 | 2.3212: Optimize plant power factor | $13,480 | $12,250 | - | - | $13,480 | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $12,250 | - |
$12,250
113,800
kWh
|
- | - | - | |
07 | 2.4133: Use most efficient type of electric motors | $64,000 | $134,000 |
$53,000
1,195,000
kWh
|
$11,000
-
kW-mo/yr
|
- | - | |
08 | 2.2136: Install / repair insulation on steam lines | $735 | $2,410 | - | - | - |
$735
-
MMBtu
|
|
TOTAL RECOMMENDED | $187,525 | $190,060 |
$97,097
2,026,509
kWh
|
$11,513
-
kW-mo/yr
|
$13,480 |
$65,435
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Wood Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs