ITAC Assessment: OR0485
ITAC logo
ITAC Assessment: OR0485
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product stud and dimensioned lumber
NAICS 321219: Reconstituted Wood Product Manufacturing
SIC 2421: Sawmills and Planing Mills, General
Sales Range $50
M
to 100
M
# of Employees 230
Plant Area 150,000
ft2
Annual Production 135,000
thousand feet
Production Hrs. Annual 8,400
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,677,620 37,812,096
kWh
Electricity Demand $303,169 70,178
kW-mo/yr
Electricity Fees $1,119 -
Fuel Oil #6 $215,630 32,714
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $187,525 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Wood Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,420 $6,500 $6,310
142,227
kWh
$110
-
kW-mo/yr
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $19,180 - $18,852
424,882
kWh
$328
-
kW-mo/yr
- -
03 2.4222: Install adequate dryers on air lines to eliminate blowdown $6,760 $15,400 $6,685
150,600
kWh
$75
-
kW-mo/yr
- -
04 2.1243: Use heat from boiler blowdown to preheat boiler feed water $64,700 $19,500 - - - $64,700
-
MMBtu
05 2.3212: Optimize plant power factor $13,480 $12,250 - - $13,480 -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $12,250 - $12,250
113,800
kWh
- - -
07 2.4133: Use most efficient type of electric motors $64,000 $134,000 $53,000
1,195,000
kWh
$11,000
-
kW-mo/yr
- -
08 2.2136: Install / repair insulation on steam lines $735 $2,410 - - - $735
-
MMBtu
TOTAL RECOMMENDED $187,525 $190,060 $97,097
2,026,509
kWh
$11,513
-
kW-mo/yr
$13,480 $65,435
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Wood Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs