Assessment Year | 2004 |
---|---|
Principal Product | Injection Molded Plastic |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
70,000
ft2
|
Annual Production | 1,200,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $104,868 | 2,491,440 |
kWh
|
$0.042 |
Electricity Demand | $48,775 | 73,140 |
kW-mo/yr
|
$0.67 |
Electricity Fees | $864 | - |
|
- |
Natural Gas | $2,157 | 193 |
MMBtu
|
$11.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,530 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,030 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|
01 | 4.441: Install automatic packing equipment | $7,000 | $7,000 | - | - | $7,000 | |
02 | 2.3212: Optimize plant power factor | $7,400 | $7,400 | - |
$7,400
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,500 | $1,500 |
$1,200
29,400
kWh
|
$300
-
kW-mo/yr
|
- | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $1,530 | $2,200 |
$1,530
37,130
kWh
|
- | - | |
05 | 2.4224: Upgrade controls on compressors | $1,100 | $4,000 |
$1,000
23,300
kWh
|
$100
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $18,530 | $22,100 |
$3,730
89,830
kWh
|
$7,800
-
kW-mo/yr
|
$7,000 | ||
TOTAL IMPLEMENTED | $10,030 | $10,700 |
$2,730
66,530
kWh
|
$300
-
kW-mo/yr
|
$7,000 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs