ITAC Assessment: OR0468
ITAC logo
ITAC Assessment: OR0468
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Brad Beavers
NAICS 321211: Hardwood Veneer and Plywood Manufacturing
SIC 2435: Hardwood Veneer and Plywood
Sales Range $10
M
to 50
M
# of Employees 158
Plant Area 100,000
ft2
Annual Production 114,729
ton
Production Hrs. Annual 7,344
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $164,020 6,797,687
kWh
Electricity Demand $61,421 209,976
kW-mo/yr
Electricity Fees $150,402 -
Natural Gas $18,989 2,905
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $319,250 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $106,700

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.5195: Change product design to reduce energy requirements $19,500 $235 $15,600
467,000
kWh
$3,900
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,200 $9,200 $8,200
246,200
kWh
$1,000
-
kW-mo/yr
- - -
03 2.5121: Redesign flow to minimize mass transfer length $3,000 - $2,600
76,000
kWh
$400
-
kW-mo/yr
- - -
04 2.4224: Upgrade controls on compressors $22,000 $1,200 $17,400
522,500
kWh
$4,600
-
kW-mo/yr
- - -
05 2.5121: Redesign flow to minimize mass transfer length $72,800 $13,600 $7,500
224,000
kWh
$3,400
-
kW-mo/yr
- $47,500 $14,400
06 2.7135: Install occupancy sensors $3,200 $3,100 $2,200
65,800
kWh
- - - $1,000
07 2.4133: Use most efficient type of electric motors $29,200 $27,800 $24,300
726,000
kWh
$4,900
-
kW-mo/yr
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $12,700 $13,800 $8,300
247,000
kWh
$1,500
-
kW-mo/yr
- $2,900 -
09 2.5121: Redesign flow to minimize mass transfer length $14,800 $15,700 $12,900
384,000
kWh
$1,900
-
kW-mo/yr
- - -
10 2.6218: Turn off equipment when not in use $15,800 $26,600 $13,200
391,500
kWh
$2,600
-
kW-mo/yr
- - -
11 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $14,650 $24,900 $12,900
386,000
kWh
$1,750
-
kW-mo/yr
- - -
12 4.445: Install equipment to move product $102,400 $242,000 - $(-3,700.0)
-
kW-mo/yr
$7,500
-
MMBtu
$98,600 -
TOTAL RECOMMENDED $319,250 $378,135 $125,100
3,736,000
kWh
$22,250
-
kW-mo/yr
$7,500
-
MMBtu
$149,000 $15,400
TOTAL IMPLEMENTED $106,700 $94,300 $86,900
2,593,200
kWh
$16,900
-
kW-mo/yr
- $2,900 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs