Assessment Year | 2004 |
---|---|
Principal Product | Brad Beavers |
NAICS | 321211: Hardwood Veneer and Plywood Manufacturing |
SIC | 2435: Hardwood Veneer and Plywood |
Sales Range | $10 M to 50M |
# of Employees | 158 |
Plant Area |
100,000
ft2
|
Annual Production | 114,729
ton
|
Production Hrs. Annual | 7,344
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $164,020 | 6,797,687 |
kWh
|
$0.024 |
Electricity Demand | $61,421 | 209,976 |
kW-mo/yr
|
$0.29 |
Electricity Fees | $150,402 | - |
|
- |
Natural Gas | $18,989 | 2,905 |
MMBtu
|
$6.54 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $319,250 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $106,700 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.5195: Change product design to reduce energy requirements | $19,500 | $235 |
$15,600
467,000
kWh
|
$3,900
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,200 | $9,200 |
$8,200
246,200
kWh
|
$1,000
-
kW-mo/yr
|
- | - | - | |
03 | 2.5121: Redesign flow to minimize mass transfer length | $3,000 | - |
$2,600
76,000
kWh
|
$400
-
kW-mo/yr
|
- | - | - | |
04 | 2.4224: Upgrade controls on compressors | $22,000 | $1,200 |
$17,400
522,500
kWh
|
$4,600
-
kW-mo/yr
|
- | - | - | |
05 | 2.5121: Redesign flow to minimize mass transfer length | $72,800 | $13,600 |
$7,500
224,000
kWh
|
$3,400
-
kW-mo/yr
|
- | $47,500 | $14,400 | |
06 | 2.7135: Install occupancy sensors | $3,200 | $3,100 |
$2,200
65,800
kWh
|
- | - | - | $1,000 | |
07 | 2.4133: Use most efficient type of electric motors | $29,200 | $27,800 |
$24,300
726,000
kWh
|
$4,900
-
kW-mo/yr
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,700 | $13,800 |
$8,300
247,000
kWh
|
$1,500
-
kW-mo/yr
|
- | $2,900 | - | |
09 | 2.5121: Redesign flow to minimize mass transfer length | $14,800 | $15,700 |
$12,900
384,000
kWh
|
$1,900
-
kW-mo/yr
|
- | - | - | |
10 | 2.6218: Turn off equipment when not in use | $15,800 | $26,600 |
$13,200
391,500
kWh
|
$2,600
-
kW-mo/yr
|
- | - | - | |
11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,650 | $24,900 |
$12,900
386,000
kWh
|
$1,750
-
kW-mo/yr
|
- | - | - | |
12 | 4.445: Install equipment to move product | $102,400 | $242,000 | - |
$(-3,700.0)
-
kW-mo/yr
|
$7,500
-
MMBtu
|
$98,600 | - | |
TOTAL RECOMMENDED | $319,250 | $378,135 |
$125,100
3,736,000
kWh
|
$22,250
-
kW-mo/yr
|
$7,500
-
MMBtu
|
$149,000 | $15,400 | ||
TOTAL IMPLEMENTED | $106,700 | $94,300 |
$86,900
2,593,200
kWh
|
$16,900
-
kW-mo/yr
|
- | $2,900 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs