Assessment Year | 2004 |
---|---|
Principal Product | Dimensional Lumber |
NAICS | 321912: Cut Stock, Resawing Lumber, and Planing |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 97 |
Plant Area |
251,121
ft2
|
Annual Production | 43,400,000
thousand feet
|
Production Hrs. Annual | 7,344
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $887,304 | 23,027,339 |
kWh
|
$0.039 |
Electricity Demand | $182,265 | 74,212 |
kW-mo/yr
|
$2.46 |
Electricity Fees | $72 | - |
|
- |
Natural Gas | $22,172 | 9,708 |
MMBtu
|
$2.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $534,195 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $99,995 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $8,400 | - |
$7,800
224,000
kWh
|
$600
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.2121: Increase amount of condensate returned | $46,600 | $14,000 | - | - |
$13,200
-
MMBtu
|
$32,300 |
$1,100
-
Tgal
|
- | - | |
03 | 4.423: Move product using mechanical means | $426,000 | $4,000 | - | - | - | - | - | $457,000 | $(-31,000.0) | |
04 | 2.2136: Install / repair insulation on steam lines | $8,200 | $5,000 |
$8,200
236,000
kWh
|
- | - | - | - | - | - | |
05 | 2.3212: Optimize plant power factor | $35,600 | $55,000 | - |
$35,600
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $5,200 | $13,400 |
$4,000
113,000
kWh
|
$1,200
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.7124: Make a practice of turning off lights when not needed | $4,195 | $2,800 |
$3,100
88,000
kWh
|
- | - | $1,095 | - | - | - | |
TOTAL RECOMMENDED | $534,195 | $94,200 |
$23,100
661,000
kWh
|
$37,400
-
kW-mo/yr
|
$13,200
-
MMBtu
|
$33,395 |
$1,100
-
Tgal
|
$457,000 | $(-31,000.0) | ||
TOTAL IMPLEMENTED | $99,995 | $85,200 |
$14,900
425,000
kWh
|
$37,400
-
kW-mo/yr
|
$13,200
-
MMBtu
|
$33,395 |
$1,100
-
Tgal
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs