ITAC Assessment: OR0465
ITAC logo
ITAC Assessment: OR0465
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Dimensional Lumber
NAICS 321912: Cut Stock, Resawing Lumber, and Planing
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 97
Plant Area 251,121
ft2
Annual Production 43,400,000
thousand feet
Production Hrs. Annual 7,344
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $887,304 23,027,339
kWh
Electricity Demand $182,265 74,212
kW-mo/yr
Electricity Fees $72 -
Natural Gas $22,172 9,708
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $534,195 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $99,995

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Wood Savings Ancillary Material Cost Savings Water Consumption Savings Primary Product Savings By-product Production Savings
01 2.4224: Upgrade controls on compressors $8,400 - $7,800
224,000
kWh
$600
-
kW-mo/yr
- - - - -
02 2.2121: Increase amount of condensate returned $46,600 $14,000 - - $13,200
-
MMBtu
$32,300 $1,100
-
Tgal
- -
03 4.423: Move product using mechanical means $426,000 $4,000 - - - - - $457,000 $(-31,000.0)
04 2.2136: Install / repair insulation on steam lines $8,200 $5,000 $8,200
236,000
kWh
- - - - - -
05 2.3212: Optimize plant power factor $35,600 $55,000 - $35,600
-
kW-mo/yr
- - - - -
06 2.4133: Use most efficient type of electric motors $5,200 $13,400 $4,000
113,000
kWh
$1,200
-
kW-mo/yr
- - - - -
07 2.7124: Make a practice of turning off lights when not needed $4,195 $2,800 $3,100
88,000
kWh
- - $1,095 - - -
TOTAL RECOMMENDED $534,195 $94,200 $23,100
661,000
kWh
$37,400
-
kW-mo/yr
$13,200
-
MMBtu
$33,395 $1,100
-
Tgal
$457,000 $(-31,000.0)
TOTAL IMPLEMENTED $99,995 $85,200 $14,900
425,000
kWh
$37,400
-
kW-mo/yr
$13,200
-
MMBtu
$33,395 $1,100
-
Tgal
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Wood Savings Ancillary Material Cost Savings Water Consumption Savings Primary Product Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs