| Assessment Year | 2004 |
|---|---|
| Principal Product | Lumber |
| NAICS | 321912: Cut Stock, Resawing Lumber, and Planing |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $10 M to 50M |
| # of Employees | 15 |
| Plant Area |
350,000
ft2
|
| Annual Production | 64,990,000
thousand feet
|
| Production Hrs. Annual | 2,783
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $161,180 | 3,209,470 |
kWh
|
$0.050 |
| Electricity Demand | $34,710 | 146,880 |
kW-mo/yr
|
$0.24 |
| Electricity Fees | $2,282 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $94,055 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $54,650 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,350 | $1,350 |
$1,150
23,000
kWh
|
$200
-
kW-mo/yr
|
- | - | |
| 02 | 2.4224: Upgrade controls on compressors | $5,200 | - |
$4,470
89,000
kWh
|
$730
-
kW-mo/yr
|
- | - | |
| 03 | 4.441: Install automatic packing equipment | $35,405 | $42,000 |
$(-123.0)
(-3,530)
kWh
|
$(-272.0)
-
kW-mo/yr
|
$35,800 | - | |
| 04 | 4.651: Install back-up equipment | $44,800 | $170 | - | - | $16,900 | $27,900 | |
| 05 | 2.4133: Use most efficient type of electric motors | $3,300 | $6,900 |
$2,700
52,900
kWh
|
$600
-
kW-mo/yr
|
- | - | |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $4,000 | $800 |
$4,000
79,820
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $94,055 | $51,220 |
$12,197
241,190
kWh
|
$1,258
-
kW-mo/yr
|
$52,700 | $27,900 | ||
| TOTAL IMPLEMENTED | $54,650 | $8,420 |
$8,320
164,900
kWh
|
$1,530
-
kW-mo/yr
|
$16,900 | $27,900 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs