Assessment Year | 2004 |
---|---|
Principal Product | Frozen Vegetables |
NAICS | 311411: Frozen Fruit, Juice, and Vegetable Manufacturing |
SIC | 2037: Frozen Fruits, Fruit Juices, and Vegetables |
Sales Range | $10 M to 50M |
# of Employees | 193 |
Plant Area |
311,000
ft2
|
Annual Production | 150,000,000
lb
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $716,741 | 20,287,360 |
kWh
|
$0.035 |
Electricity Demand | $219,800 | 49,010 |
kW-mo/yr
|
$4.48 |
Electricity Fees | $19,157 | - |
|
- |
Natural Gas | $167,716 | 32,786 |
MMBtu
|
$5.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $61,380 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $56,880 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $4,500 | $10,500 |
$4,500
143,400
kWh
|
- | - | - | |
02 | 2.2621: Modify refrigeration system to operate at a lower pressure | $9,750 | $300 |
$9,750
309,400
kWh
|
- | - | - | |
03 | 2.4224: Upgrade controls on compressors | $4,820 | $36,600 |
$4,200
133,000
kWh
|
$620
-
kW-mo/yr
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $34,250 | $2,000 |
$27,400
874,000
kWh
|
$6,850
-
kW-mo/yr
|
- | - | |
05 | 2.1231: Establish burner maintenance schedule for boilers | $5,330 | $2,825 | - | - | - |
$5,330
-
MMBtu
|
|
06 | 2.3212: Optimize plant power factor | $2,730 | $5,130 | - | - | $2,730 | - | |
TOTAL RECOMMENDED | $61,380 | $57,355 |
$45,850
1,459,800
kWh
|
$7,470
-
kW-mo/yr
|
$2,730 |
$5,330
-
MMBtu
|
||
TOTAL IMPLEMENTED | $56,880 | $46,855 |
$41,350
1,316,400
kWh
|
$7,470
-
kW-mo/yr
|
$2,730 |
$5,330
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs