| Assessment Year | 2004 |
|---|---|
| Principal Product | Corrugated Cardboard |
| NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
516,478
ft2
|
| Annual Production | 869,000,000
thousand feet
|
| Production Hrs. Annual | 6,600
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $238,437 | 5,677,080 |
kWh
|
$0.042 |
| Electricity Demand | $47,231 | 10,933 |
kW-mo/yr
|
$4.32 |
| Electricity Fees | $18,203 | - |
|
- |
| Natural Gas | $250,311 | 51,539 |
MMBtu
|
$4.86 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $124,535 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $118,600 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.625: Develop standard operating procedures | $106,000 | - | - | - | - | $106,000 | |
| 02 | 2.4133: Use most efficient type of electric motors | $6,280 | $7,540 |
$5,040
120,000
kWh
|
$1,240
-
kW-mo/yr
|
- | - | |
| 03 | 2.6218: Turn off equipment when not in use | $2,335 | $4,025 |
$2,335
60,700
kWh
|
- | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $900 | $900 |
$900
20,000
kWh
|
- | - | - | |
| 05 | 2.4224: Upgrade controls on compressors | $3,600 | $4,000 |
$3,000
71,000
kWh
|
$600
-
kW-mo/yr
|
- | - | |
| 06 | 2.2211: Use optimum temperature | $5,420 | $7,880 |
$880
107
kWh
|
- |
$4,540
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $124,535 | $24,345 |
$12,155
271,807
kWh
|
$1,840
-
kW-mo/yr
|
$4,540
-
MMBtu
|
$106,000 | ||
| TOTAL IMPLEMENTED | $118,600 | $16,320 |
$6,820
140,107
kWh
|
$1,240
-
kW-mo/yr
|
$4,540
-
MMBtu
|
$106,000 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs