| Assessment Year | 2003 |
|---|---|
| Principal Product | Cheese |
| NAICS | 311513: Cheese Manufacturing |
| SIC | 2022: Natural, Processed, and Imitation Cheese |
| Sales Range | $50 M to 100M |
| # of Employees | 60 |
| Plant Area |
n/a
|
| Annual Production | 42,536,000
lb
|
| Production Hrs. Annual | 5,616
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $376,349 | 8,863,440 |
kWh
|
$0.042 |
| Electricity Demand | $66,874 | 18,576 |
kW-mo/yr
|
$3.60 |
| Electricity Fees | $4,670 | - |
|
- |
| Other Energy | $293,815 | 56,668 |
MMBtu
|
$5.18 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $72,600 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $32,870 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings | Personnel Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2127: Flash condensate to produce lower pressure steam | $27,900 | $23,290 | - | - |
$27,900
-
MMBtu
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $21,500 | $11,700 |
$18,220
437,500
kWh
|
$3,280
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7134: Use photocell controls | $11,250 | $1,340 |
$7,020
161,000
kWh
|
- | - | $670 | $3,560 | |
| 04 | 2.2621: Modify refrigeration system to operate at a lower pressure | $7,900 | - |
$7,900
189,700
kWh
|
- | - | - | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,470 | - |
$3,010
68,000
kWh
|
$460
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4145: Install isolation transformer on adjustable frequency drive | $580 | $1,400 |
$490
11,800
kWh
|
$90
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $72,600 | $37,730 |
$36,640
868,000
kWh
|
$3,830
-
kW-mo/yr
|
$27,900
-
MMBtu
|
$670 | $3,560 | ||
| TOTAL IMPLEMENTED | $32,870 | $11,700 |
$29,130
695,200
kWh
|
$3,740
-
kW-mo/yr
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings | Personnel Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs