| Assessment Year | 2004 |
|---|---|
| Principal Product | powder metal parts |
| NAICS | 332117: Powder Metallurgy Part Manufacturing |
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 213 |
| Plant Area |
96,475
ft2
|
| Annual Production | 45,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $139,352 | 8,023,500 |
kWh
|
$0.017 |
| Electricity Demand | $98,985 | 19,629 |
kW-mo/yr
|
$5.04 |
| Electricity Fees | $(-10,567.0) | - |
|
- |
| Natural Gas | $303,786 | 43,294 |
MMBtu
|
$7.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $218,503 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $40,084 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 4.212: Adopt in-house material generation | $174,960 | $252,000 | - | - | $174,960 | |
| 02 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $20,082 | $7,750 | - |
$20,082
-
MMBtu
|
- | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $10,788 | $12,000 | - |
$10,788
-
MMBtu
|
- | |
| 04 | 2.3212: Optimize plant power factor | $5,122 | $6,750 |
$5,122
-
kW-mo/yr
|
- | - | |
| 05 | 2.1114: Limit and control secondary combustion air in furnace | $4,092 | $6,000 | - |
$4,092
-
MMBtu
|
- | |
| 06 | 2.2437: Recover waste heat from equipment | $3,459 | $2,888 | - |
$3,459
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $218,503 | $287,388 |
$5,122
-
kW-mo/yr
|
$38,421
-
MMBtu
|
$174,960 | ||
| TOTAL IMPLEMENTED | $40,084 | $32,500 |
$5,122
-
kW-mo/yr
|
$34,962
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs