Assessment Year | 2003 |
---|---|
Principal Product | Canned Beans, Soup |
NAICS | 311422: Specialty Canning |
SIC | 2032: Canned Specialties |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
n/a
|
Annual Production | 40,000,000
pieces
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $210,307 | 7,183,129 |
kWh
|
$0.029 |
Electricity Demand | $55,186 | 191,700 |
kW-mo/yr
|
$0.29 |
Electricity Fees | $14,303 | - |
|
- |
Natural Gas | $860,719 | 165,377 |
MMBtu
|
$5.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $370,250 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $353,650 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.3128: Utilize other methods to remove contaminants | $330,000 | $790,000 |
$(-20,000.0)
(-650,000)
kWh
|
- | - | - |
$350,000
-
lb
|
- | - | |
02 | 2.2121: Increase amount of condensate returned | $13,400 | $28,000 | - | - |
$13,400
-
MMBtu
|
- | - | - | - | |
03 | 2.1133: Adjust burners for efficient operation | $10,500 | $450 | - | - |
$11,400
-
MMBtu
|
- | - | $(-900.0) | - | |
04 | 2.2136: Install / repair insulation on steam lines | $4,500 | $1,850 | - | - | - |
$4,500
-
MMBtu
|
- | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $5,400 | $12,100 |
$4,280
147,000
kWh
|
$1,120
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.2161: Optimize operation of multi-stage vacuum steam jets | $3,250 | $3,000 | - | - | - | - | - | - | $3,250 | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,940 | $1,850 |
$782
26,900
kWh
|
$264
-
kW-mo/yr
|
- | - | - | $894 | - | |
08 | 2.4224: Upgrade controls on compressors | $1,260 | $495 |
$1,000
34,400
kWh
|
$260
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $370,250 | $837,745 |
$(-13,938.0)
(-441,700)
kWh
|
$1,644
-
kW-mo/yr
|
$24,800
-
MMBtu
|
$4,500
-
MMBtu
|
$350,000
-
lb
|
$(-6.0) | $3,250 | ||
TOTAL IMPLEMENTED | $353,650 | $807,400 |
$(-15,720.0)
(-503,000)
kWh
|
$1,120
-
kW-mo/yr
|
$11,400
-
MMBtu
|
$4,500
-
MMBtu
|
$350,000
-
lb
|
$(-900.0) | $3,250 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs