Assessment Year | 2003 |
---|---|
Principal Product | Folding handtools, Knives |
NAICS | 332215: Metal Kitchen Cookware, Utensil, Cutlery, and Flatware (except Precious) Manufacturing |
SIC | 2134: |
Sales Range | $50 M to 100M |
# of Employees | 254 |
Plant Area |
77,862
ft2
|
Annual Production | 1,570,000
pieces
|
Production Hrs. Annual | 4,916
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $174,743 | 3,858,320 |
kWh
|
$0.045 |
Electricity Demand | $53,116 | 11,040 |
kW-mo/yr
|
$4.81 |
Electricity Fees | $1,381 | - |
|
- |
Natural Gas | $45,235 | 6,794 |
MMBtu
|
$6.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $129,040 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,450 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8211: Consolidate freight shipments and/or deliveries | $78,000 | $44,800 | n/a | - | - | - | $74,200 | $3,800 |
02 | 2.6242: Minimize operation of equipment maintained in standby condition | $32,000 | $1,500 | - | - |
$32,000
-
MMBtu
|
- | - | |
03 | 2.4224: Upgrade controls on compressors | $12,600 | $5,000 |
$9,300
206,000
kWh
|
$3,300
-
kW-mo/yr
|
- | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $5,850 | $8,350 |
$4,140
91,400
kWh
|
$1,710
-
kW-mo/yr
|
- | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $590 | - |
$390
8,700
kWh
|
$200
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $129,040 | $59,650 |
$13,830
306,100
kWh
|
$5,210
-
kW-mo/yr
|
$32,000
-
MMBtu
|
$74,200 | $3,800 | ||
TOTAL IMPLEMENTED | $18,450 | $13,350 |
$13,440
297,400
kWh
|
$5,010
-
kW-mo/yr
|
- | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs