| Assessment Year | 2003 |
|---|---|
| Principal Product | Plywood |
| NAICS | 321212: Softwood Veneer and Plywood Manufacturing |
| SIC | 2436: Softwood Veneer and Plywood |
| Sales Range | $100 M to 500M |
| # of Employees | 228 |
| Plant Area |
180,000
ft2
|
| Annual Production | 25,000,000
pieces
|
| Production Hrs. Annual | 4,966
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $566,504 | 13,186,860 |
kWh
|
$0.043 |
| Electricity Demand | $241,338 | 395,604 |
kW-mo/yr
|
$0.61 |
| Electricity Fees | $43,800 | - |
|
- |
| Natural Gas | $299,947 | 50,184 |
MMBtu
|
$5.98 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $345,146 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $63,530 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.441: Install automatic packing equipment | $119,450 | $176,200 |
$(-290.0)
(-8,184)
kWh
|
$(-260.0)
-
kW-mo/yr
|
- | - | $120,000 | - | - | |
| 02 | 4.423: Move product using mechanical means | $129,340 | $12,250 |
$(-660.0)
(-18,732)
kWh
|
- | - | - | $40,000 | $90,000 | - | |
| 03 | 4.445: Install equipment to move product | $11,900 | $9,300 | - | - |
$1,125
-
MMBtu
|
- | $10,000 | $775 | - | |
| 04 | 2.4112: Install soft-start to eliminate nuisance trips | $30,700 | $17,700 |
$19,900
497,300
kWh
|
$10,800
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,810 | $9,000 |
$7,480
212,780
kWh
|
$1,330
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 2.4224: Upgrade controls on compressors | $11,350 | $2,000 |
$8,050
228,660
kWh
|
$3,300
-
kW-mo/yr
|
- | - | - | - | - | |
| 07 | 2.4226: Use / purchase optimum sized compressor | $2,950 | $3,100 |
$2,950
83,830
kWh
|
- | - | - | - | - | - | |
| 08 | 2.2136: Install / repair insulation on steam lines | $8,830 | $14,600 |
$7,430
211,200
kWh
|
$1,400
-
kW-mo/yr
|
- | - | - | - | - | |
| 09 | 2.4133: Use most efficient type of electric motors | $3,840 | $1,270 |
$2,520
71,474
kWh
|
$1,320
-
kW-mo/yr
|
- | - | - | - | - | |
| 10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $816 | - |
$574
16,300
kWh
|
$242
-
kW-mo/yr
|
- | - | - | - | - | |
| 11 | 3.1161: Eliminate/reduce an operation | $17,160 | $16,900 | - | - | - |
$420
-
lb
|
- | - | $16,740 | |
| TOTAL RECOMMENDED | $345,146 | $262,320 |
$47,954
1,294,628
kWh
|
$18,132
-
kW-mo/yr
|
$1,125
-
MMBtu
|
$420
-
lb
|
$170,000 | $90,775 | $16,740 | ||
| TOTAL IMPLEMENTED | $63,530 | $44,570 |
$45,380
1,221,414
kWh
|
$18,150
-
kW-mo/yr
|
- | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs