ITAC Assessment: OR0430
ITAC logo
ITAC Assessment: OR0430
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Plywood
NAICS 321212: Softwood Veneer and Plywood Manufacturing
SIC 2436: Softwood Veneer and Plywood
Sales Range $100
M
to 500
M
# of Employees 228
Plant Area 180,000
ft2
Annual Production 25,000,000
pieces
Production Hrs. Annual 4,966
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $566,504 13,186,860
kWh
Electricity Demand $241,338 395,604
kW-mo/yr
Electricity Fees $43,800 -
Natural Gas $299,947 50,184
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $345,146 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $63,530

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 4.441: Install automatic packing equipment $119,450 $176,200 $(-290.0)
(-8,184)
kWh
$(-260.0)
-
kW-mo/yr
- - $120,000 - -
02 4.423: Move product using mechanical means $129,340 $12,250 $(-660.0)
(-18,732)
kWh
- - - $40,000 $90,000 -
03 4.445: Install equipment to move product $11,900 $9,300 - - $1,125
-
MMBtu
- $10,000 $775 -
04 2.4112: Install soft-start to eliminate nuisance trips $30,700 $17,700 $19,900
497,300
kWh
$10,800
-
kW-mo/yr
- - - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,810 $9,000 $7,480
212,780
kWh
$1,330
-
kW-mo/yr
- - - - -
06 2.4224: Upgrade controls on compressors $11,350 $2,000 $8,050
228,660
kWh
$3,300
-
kW-mo/yr
- - - - -
07 2.4226: Use / purchase optimum sized compressor $2,950 $3,100 $2,950
83,830
kWh
- - - - - -
08 2.2136: Install / repair insulation on steam lines $8,830 $14,600 $7,430
211,200
kWh
$1,400
-
kW-mo/yr
- - - - -
09 2.4133: Use most efficient type of electric motors $3,840 $1,270 $2,520
71,474
kWh
$1,320
-
kW-mo/yr
- - - - -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $816 - $574
16,300
kWh
$242
-
kW-mo/yr
- - - - -
11 3.1161: Eliminate/reduce an operation $17,160 $16,900 - - - $420
-
lb
- - $16,740
TOTAL RECOMMENDED $345,146 $262,320 $47,954
1,294,628
kWh
$18,132
-
kW-mo/yr
$1,125
-
MMBtu
$420
-
lb
$170,000 $90,775 $16,740
TOTAL IMPLEMENTED $63,530 $44,570 $45,380
1,221,414
kWh
$18,150
-
kW-mo/yr
- - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs