Assessment Year | 2002 |
---|---|
Principal Product | roofing material |
NAICS |
n/a
|
SIC | 2952: Asphalt Felts and Coatings |
Sales Range | $100 M to 500M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 200,000
ton
|
Production Hrs. Annual | 7,056
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $185,009 | 5,858,800 |
kWh
|
$0.032 |
Electricity Demand | $51,783 | 10,860 |
kW-mo/yr
|
$4.77 |
Electricity Fees | $1,614 | - |
|
- |
Natural Gas | $324,311 | 78,356 |
MMBtu
|
$4.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,000 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,000 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,409 | $1,400 |
$1,174
37,178
kWh
|
$235
-
kW-mo/yr
|
- | - | |
02 | 2.4224: Upgrade controls on compressors | $6,865 | $7,600 |
$5,623
178,068
kWh
|
$1,242
-
kW-mo/yr
|
- | - | |
03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,090 | $1,800 |
$751
23,756
kWh
|
- | - | $339 | |
04 | 2.3212: Optimize plant power factor | $929 | $1,500 | - | - | $929 | - | |
05 | 2.4133: Use most efficient type of electric motors | $4,707 | $9,446 |
$1,616
51,290
kWh
|
$3,091
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $15,000 | $21,746 |
$9,164
290,292
kWh
|
$4,568
-
kW-mo/yr
|
$929 | $339 | ||
TOTAL IMPLEMENTED | $15,000 | $21,746 |
$9,164
290,292
kWh
|
$4,568
-
kW-mo/yr
|
$929 | $339 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs