ITAC Assessment: OR0410
ITAC logo
ITAC Assessment: OR0410
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Hops extract
NAICS
n/a
SIC 2087: Flavoring Extracts and Flavoring Syrups, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 40
Plant Area
n/a
Annual Production 1,170,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $175,339 5,138,560
kWh
Electricity Demand $40,514 12,204
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,626 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,265

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.2621: Modify refrigeration system to operate at a lower pressure $17,362 - $17,362
515,638
kWh
-
02 2.4133: Use most efficient type of electric motors $8,208 $22,848 $6,559
196,504
kWh
$1,649
-
kW-mo/yr
03 2.4224: Upgrade controls on compressors $3,700 $2,000 $3,186
95,460
kWh
$514
-
kW-mo/yr
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,057 $4,025 $2,690
80,592
kWh
$367
-
kW-mo/yr
05 2.7124: Make a practice of turning off lights when not needed $299 $600 $263
7,884
kWh
$36
-
kW-mo/yr
TOTAL RECOMMENDED $32,626 $29,473 $30,060
896,078
kWh
$2,566
-
kW-mo/yr
TOTAL IMPLEMENTED $11,265 $26,873 $9,249
277,096
kWh
$2,016
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs