Assessment Year | 2002 |
---|---|
Principal Product | Particle Board |
NAICS |
n/a
|
SIC | 2493: Reconstituted Wood Products |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
n/a
|
Annual Production | 132,000
thousand feet
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,037,873 | 42,431,437 |
kWh
|
$0.024 |
Electricity Demand | $228,741 | 71,928 |
kW-mo/yr
|
$3.18 |
Electricity Fees | $56,144 | - |
|
- |
Natural Gas | $618,931 | 91,714 |
MMBtu
|
$6.75 |
Wood | $563,244 | 197,587 |
MMBtu
|
$2.85 |
Other Energy | $540,180 | 140,306 |
MMBtu
|
$3.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $280,995 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,596 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Wood Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1331: Burn a less expensive grade of fuel | $139,631 | $27,000 | - | - | - |
$246,191
-
MMBtu
|
$(-105,060.0)
-
MMBtu
|
- | $(-1,500.0) | - | |
02 | 2.3212: Optimize plant power factor | $50,372 | $92,500 | - | - | $50,372 | - | - | - | - | - | |
03 | 4.653: Maintain/enlarge a stock of spare parts | $29,530 | $43,240 | - | - | - | - | - | $390 | $2,140 | $27,000 | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $20,752 | - |
$16,719
784,009
kWh
|
$4,033
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,569 | $8,500 |
$7,065
331,225
kWh
|
$1,504
-
kW-mo/yr
|
- | - | - | - | - | - | |
06 | 2.4224: Upgrade controls on compressors | $12,899 | - |
$10,857
508,993
kWh
|
$2,042
-
kW-mo/yr
|
- | - | - | - | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,215 | $60,000 |
$8,887
417,240
kWh
|
$2,328
-
kW-mo/yr
|
- | - | - | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,027 | $3,630 |
$4,745
222,504
kWh
|
$970
-
kW-mo/yr
|
- | - | - | $(-566.0) | $2,878 | - | |
TOTAL RECOMMENDED | $280,995 | $234,870 |
$48,273
2,263,971
kWh
|
$10,877
-
kW-mo/yr
|
$50,372 |
$246,191
-
MMBtu
|
$(-105,060.0)
-
MMBtu
|
$(-176.0) | $3,518 | $27,000 | ||
TOTAL IMPLEMENTED | $16,596 | $12,130 |
$11,810
553,729
kWh
|
$2,474
-
kW-mo/yr
|
- | - | - | $(-566.0) | $2,878 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Wood Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs