Assessment Year | 2001 |
---|---|
Principal Product | Lumber |
NAICS |
n/a
|
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 119 |
Plant Area |
n/a
|
Annual Production | 111,461
thousand feet
|
Production Hrs. Annual | 4,518
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $239,996 | 7,741,800 |
kWh
|
$0.031 |
Electricity Demand | $64,989 | 20,628 |
kW-mo/yr
|
$3.15 |
Electricity Fees | $64,156 | - |
|
- |
Natural Gas | $1,155 | 138 |
MMBtu
|
$8.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,301,444 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $916,086 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.445: Install equipment to move product | $265,366 | $900,000 |
$(-1,867.0)
(-60,240)
kWh
|
$(-567.0)
-
kW-mo/yr
|
- | $284,300 | $(-16,500.0) | - | |
02 | 4.132: Purchase new equipment to reduce material use / cost | $879,623 | $145,450 |
$1,245
40,160
kWh
|
$378
-
kW-mo/yr
|
- | - | - | $878,000 | |
03 | 4.642: Install sensors to detect and avoid jams | $116,900 | $20,000 | - | - | - | - | $(-1,100.0) | $118,000 | |
04 | 2.3212: Optimize plant power factor | $17,987 | $28,200 | - | - | $17,987 | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,599 | $4,500 |
$3,900
125,816
kWh
|
$699
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4224: Upgrade controls on compressors | $13,877 | $4,000 |
$13,284
428,510
kWh
|
$593
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4322: Use or replace with energy efficient substitutes | $3,092 | $13,700 |
$2,372
76,500
kWh
|
$720
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $1,301,444 | $1,115,850 |
$18,934
610,746
kWh
|
$1,823
-
kW-mo/yr
|
$17,987 | $284,300 | $(-17,600.0) | $996,000 | ||
TOTAL IMPLEMENTED | $916,086 | $182,150 |
$18,429
594,486
kWh
|
$1,670
-
kW-mo/yr
|
$17,987 | - | - | $878,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs