Assessment Year | 2001 |
---|---|
Principal Product | Aluminum/Steel Boxes |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
70,000
ft2
|
Annual Production | 36,000
pieces
|
Production Hrs. Annual | 4,498
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,888 | 982,300 |
kWh
|
$0.037 |
Electricity Demand | $12,260 | 2,652 |
kW-mo/yr
|
$4.62 |
Electricity Fees | $2,555 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $88,355 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $84,826 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.132: Purchase new equipment to reduce material use / cost | $79,800 | $30,700 | - | - | - | $13,350 | $66,450 | |
02 | 2.3212: Optimize plant power factor | $2,467 | $2,100 | - | - | $2,467 | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,749 | $1,700 |
$1,286
35,225
kWh
|
$463
-
kW-mo/yr
|
- | - | - | |
04 | 2.4226: Use / purchase optimum sized compressor | $3,277 | $2,100 |
$2,408
65,975
kWh
|
$869
-
kW-mo/yr
|
- | - | - | |
05 | 2.8112: Combine utility meters | $1,062 | $3,925 | - |
$(-985.0)
-
kW-mo/yr
|
$2,047 | - | - | |
TOTAL RECOMMENDED | $88,355 | $40,525 |
$3,694
101,200
kWh
|
$347
-
kW-mo/yr
|
$4,514 | $13,350 | $66,450 | ||
TOTAL IMPLEMENTED | $84,826 | $34,500 |
$3,694
101,200
kWh
|
$1,332
-
kW-mo/yr
|
- | $13,350 | $66,450 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs