Assessment Year | 2000 |
---|---|
Principal Product | Lumber |
NAICS |
n/a
|
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $50 M to 100M |
# of Employees | 135 |
Plant Area |
n/a
|
Annual Production | 140,385
thousand feet
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $249,095 | 7,273,447 |
kWh
|
$0.034 |
Electricity Demand | $64,243 | 223,824 |
kW-mo/yr
|
$0.29 |
Electricity Fees | $12,018 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $134,205 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,059 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.111: Add equipment/ operators to reduce production bottleneck | $89,400 | $280,000 | - | - | - | - | $19,200 | - | $70,200 | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $15,389 | $29,590 |
$15,389
449,297
kWh
|
- | - | - | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $15,954 | $30,046 |
$12,532
365,768
kWh
|
$3,422
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.3212: Optimize plant power factor | $4,853 | $13,600 | - | - | $4,853 | - | - | - | - | |
05 | 2.7134: Use photocell controls | $3,605 | $605 |
$2,873
84,701
kWh
|
- | - | - | - | $732 | - | |
06 | 2.4224: Upgrade controls on compressors | $647 | - |
$647
18,757
kWh
|
- | - | - | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,013 | - |
$2,577
75,322
kWh
|
$436
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,344 | $7,500 |
$993
29,015
kWh
|
$206
-
kW-mo/yr
|
- |
$225
-
gal
|
$(-80.0) | - | - | |
TOTAL RECOMMENDED | $134,205 | $361,341 |
$35,011
1,022,860
kWh
|
$4,064
-
kW-mo/yr
|
$4,853 |
$225
-
gal
|
$19,120 | $732 | $70,200 | ||
TOTAL IMPLEMENTED | $25,059 | $44,251 |
$16,052
469,226
kWh
|
$3,422
-
kW-mo/yr
|
$4,853 | - | - | $732 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs