ITAC Assessment: OR0356
ITAC logo
ITAC Assessment: OR0356
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Wood Furniture
NAICS
n/a
SIC 2511: Wood Household Furniture, Except Upholstered
Sales Range $1
M
to 5
M
# of Employees 45
Plant Area 14,000
ft2
Annual Production 600,000
units
Production Hrs. Annual 2,600
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $29,463 625,733
kWh
Electricity Demand $4,378 27,216
kW-mo/yr
Electricity Fees $2,017 -
Natural Gas $4,970 837
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,527 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $911

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.3212: Optimize plant power factor $616 $1,800 - - $616
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $103 $400 $92
2,052
kWh
$11
-
kW-mo/yr
-
03 2.4224: Upgrade controls on compressors $808 - $652
14,361
kWh
$156
-
kW-mo/yr
-
TOTAL RECOMMENDED $1,527 $2,200 $744
16,413
kWh
$167
-
kW-mo/yr
$616
TOTAL IMPLEMENTED $911 $400 $744
16,413
kWh
$167
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs