| Assessment Year | 1999 |
|---|---|
| Principal Product | Particle Board |
| NAICS |
n/a
|
| SIC | 2493: Reconstituted Wood Products |
| Sales Range | $10 M to 50M |
| # of Employees | 64 |
| Plant Area |
96,570
ft2
|
| Annual Production | 70,135
thousand feet
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $403,458 | 15,606,096 |
kWh
|
$0.026 |
| Electricity Demand | $66,000 | 314,652 |
kW-mo/yr
|
$0.21 |
| Electricity Fees | $(-2,622.0) | - |
|
- |
| Natural Gas | $12,868 | 3,534 |
MMBtu
|
$3.64 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $313,459 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $78,343 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $40,560 | $64,125 |
$40,560
1,568,875
kWh
|
- | - | - | |
| 02 | 4.652: Replace existing equipment with more suitable substitutes | $36,220 | $98,500 |
$5,840
225,674
kWh
|
$2,300 | $22,000 | $6,080 | |
| 03 | 2.4325: Upgrade conveyors | $18,725 | $46,000 |
$18,725
724,209
kWh
|
- | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,088 | $10,000 |
$13,088
506,155
kWh
|
- | - | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,171 | - |
$1,171
45,428
kWh
|
- | - | - | |
| 06 | 2.4224: Upgrade controls on compressors | $24,695 | $2,840 |
$24,695
955,158
kWh
|
- | - | - | |
| 07 | 3.2176: Increase use of automation | $179,000 | $42,000 | - | $179,000 | - | - | |
| TOTAL RECOMMENDED | $313,459 | $263,465 |
$104,079
4,025,499
kWh
|
$181,300 | $22,000 | $6,080 | ||
| TOTAL IMPLEMENTED | $78,343 | $76,965 |
$78,343
3,030,188
kWh
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs