Assessment Year | 1999 |
---|---|
Principal Product | Pumps |
NAICS |
n/a
|
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
n/a
|
Annual Production | 86,000
pieces
|
Production Hrs. Annual | 5,148
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $37,704 | 1,682,005 |
kWh
|
$0.022 |
Electricity Demand | $15,259 | 45,648 |
kW-mo/yr
|
$0.33 |
Electricity Fees | $2,433 | - |
|
- |
Natural Gas | $8,001 | 1,148 |
MMBtu
|
$6.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $185,880 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $129,400 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.513: Re-arrange equipment layout to reduce labor costs | $129,400 | $58,090 | - | - | - | $129,400 | - | |
02 | 4.621: Use fixtures to reduce machine changeout times | $44,400 | $5,000 | - | - | - | $20,600 | $23,800 | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,339 | $2,000 |
$1,339
40,739
kWh
|
- | - | - | - | |
04 | 2.4224: Upgrade controls on compressors | $3,664 | $1,430 |
$3,664
111,372
kWh
|
- | - | - | - | |
05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $7,077 | $24,750 |
$(-26.0)
(-1,172)
kWh
|
$(-37.0)
-
kW-mo/yr
|
$7,140
-
lb
|
- | - | |
TOTAL RECOMMENDED | $185,880 | $91,270 |
$4,977
150,939
kWh
|
$(-37.0)
-
kW-mo/yr
|
$7,140
-
lb
|
$150,000 | $23,800 | ||
TOTAL IMPLEMENTED | $129,400 | $58,090 | - | - | - | $129,400 | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs