ITAC Assessment: OR0344
ITAC logo
ITAC Assessment: OR0344
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Wood Furniture
NAICS
n/a
SIC 2511: Wood Household Furniture, Except Upholstered
Sales Range $5
M
to 10
M
# of Employees 140
Plant Area 43,500
ft2
Annual Production 2,583,000
thousand feet
Production Hrs. Annual 4,750
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $78,104 2,332,943
kWh
Electricity Demand $20,347 77,628
kW-mo/yr
Electricity Fees $10,286 -
Natural Gas $9,906 2,094
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $168,788 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $45,746

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings
01 4.421: Modify current incentive program $94,000 $23,300 - - - $94,000
02 4.513: Re-arrange equipment layout to reduce labor costs $35,970 $40,000 - $(-530.0)
-
kW-mo/yr
- $36,500
03 4.513: Re-arrange equipment layout to reduce labor costs $7,100 $6,920 - - - $7,100
04 4.421: Modify current incentive program $6,490 $6,300 - - - $6,490
05 2.4322: Use or replace with energy efficient substitutes $9,200 $22,400 $7,360
216,589
kWh
$1,840
-
kW-mo/yr
- -
06 2.3212: Optimize plant power factor $1,915 $5,400 - - $1,915 -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,286 $1,000 $2,655
77,960
kWh
$631
-
kW-mo/yr
- -
08 2.4224: Upgrade controls on compressors $10,827 $1,210 $8,810
259,086
kWh
$2,017
-
kW-mo/yr
- -
TOTAL RECOMMENDED $168,788 $106,530 $18,825
553,635
kWh
$3,958
-
kW-mo/yr
$1,915 $144,090
TOTAL IMPLEMENTED $45,746 $47,300 $2,655
77,960
kWh
$101
-
kW-mo/yr
- $42,990
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs