Assessment Year | 1998 |
---|---|
Principal Product | Particleboard |
NAICS |
n/a
|
SIC | 2493: Reconstituted Wood Products |
Sales Range | $10 M to 50M |
# of Employees | 177 |
Plant Area |
914,760
ft2
|
Annual Production | 183,866,079
thousand feet
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,367,351 | 41,073,565 |
kWh
|
$0.033 |
Electricity Demand | $249,859 | 931,152 |
kW-mo/yr
|
$0.27 |
Electricity Fees | $12,278 | - |
|
- |
Natural Gas | $1,200,955 | 525,556 |
MMBtu
|
$2.29 |
LPG | $36,521 | 6,109 |
MMBtu
|
$5.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $352,321 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $80,024 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1231: Establish burner maintenance schedule for boilers | $77,144 | $350,000 | - | - |
$77,144
-
MMBtu
|
- | - | - | |
02 | 2.1231: Establish burner maintenance schedule for boilers | $5,644 | - | - | - |
$5,644
-
MMBtu
|
- | - | - | |
03 | 2.2437: Recover waste heat from equipment | $53,320 | $75,400 |
$(-9,760.0)
(-293,376)
kWh
|
$(-1,350.0)
-
kW-mo/yr
|
$64,430
-
MMBtu
|
- | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $19,647 | $87,375 |
$16,251
488,277
kWh
|
$3,396
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.3212: Optimize plant power factor | - | $54,400 | - | - | - | - | - | - | |
06 | 2.6218: Turn off equipment when not in use | $5,450 | - |
$5,450
163,540
kWh
|
- | - | - | - | - | |
07 | 2.4224: Upgrade controls on compressors | $2,696 | $1,200 |
$2,035
115,768
kWh
|
$661
-
kW-mo/yr
|
- | - | - | - | |
08 | 3.2111: Install redundant equipment to avoid losses caused by equipment failure and routine maintenance | $16,275 | $7,000 | - | - | - | - | - | $16,275 | |
09 | 4.651: Install back-up equipment | $103,215 | $408,000 | - | - | - | - | - | $103,215 | |
10 | 3.3133: Use other waste concentration methods | $68,930 | $131,400 |
$(-3,470.0)
(-104,045)
kWh
|
- | - |
$12,800
-
lb
|
$59,600 | - | |
TOTAL RECOMMENDED | $352,321 | $1,114,775 |
$10,506
370,164
kWh
|
$2,707
-
kW-mo/yr
|
$147,218
-
MMBtu
|
$12,800
-
lb
|
$59,600 | $119,490 | ||
TOTAL IMPLEMENTED | $80,024 | $185,800 |
$1,980
59,495
kWh
|
- |
$5,644
-
MMBtu
|
$12,800
-
lb
|
$59,600 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs