ITAC Assessment: OR0332
ITAC logo
ITAC Assessment: OR0332
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Particleboard
NAICS
n/a
SIC 2493: Reconstituted Wood Products
Sales Range $10
M
to 50
M
# of Employees 177
Plant Area 914,760
ft2
Annual Production 183,866,079
thousand feet
Production Hrs. Annual 8,400
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,367,351 41,073,565
kWh
Electricity Demand $249,859 931,152
kW-mo/yr
Electricity Fees $12,278 -
Natural Gas $1,200,955 525,556
MMBtu
LPG $36,521 6,109
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $352,321 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $80,024

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Raw Material Savings Primary Product Savings
01 2.1231: Establish burner maintenance schedule for boilers $77,144 $350,000 - - $77,144
-
MMBtu
- - -
02 2.1231: Establish burner maintenance schedule for boilers $5,644 - - - $5,644
-
MMBtu
- - -
03 2.2437: Recover waste heat from equipment $53,320 $75,400 $(-9,760.0)
(-293,376)
kWh
$(-1,350.0)
-
kW-mo/yr
$64,430
-
MMBtu
- - -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $19,647 $87,375 $16,251
488,277
kWh
$3,396
-
kW-mo/yr
- - - -
05 2.3212: Optimize plant power factor - $54,400 - - - - - -
06 2.6218: Turn off equipment when not in use $5,450 - $5,450
163,540
kWh
- - - - -
07 2.4224: Upgrade controls on compressors $2,696 $1,200 $2,035
115,768
kWh
$661
-
kW-mo/yr
- - - -
08 3.2111: Install redundant equipment to avoid losses caused by equipment failure and routine maintenance $16,275 $7,000 - - - - - $16,275
09 4.651: Install back-up equipment $103,215 $408,000 - - - - - $103,215
10 3.3133: Use other waste concentration methods $68,930 $131,400 $(-3,470.0)
(-104,045)
kWh
- - $12,800
-
lb
$59,600 -
TOTAL RECOMMENDED $352,321 $1,114,775 $10,506
370,164
kWh
$2,707
-
kW-mo/yr
$147,218
-
MMBtu
$12,800
-
lb
$59,600 $119,490
TOTAL IMPLEMENTED $80,024 $185,800 $1,980
59,495
kWh
- $5,644
-
MMBtu
$12,800
-
lb
$59,600 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Raw Material Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs