Assessment Year | 1998 |
---|---|
Principal Product | Investment Castings |
NAICS |
n/a
|
SIC | 3724: Aircraft Engines and Engine Parts |
Sales Range | $50 M to 100M |
# of Employees | 600 |
Plant Area |
203,696
ft2
|
Annual Production | 3,172,304
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $545,564 | 31,300,704 |
kWh
|
$0.017 |
Electricity Demand | $376,763 | 661,956 |
kW-mo/yr
|
$0.57 |
Electricity Fees | $9,453 | - |
|
- |
Natural Gas | $476,523 | 144,972 |
MMBtu
|
$3.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $246,504 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $194,253 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,329 | $15,000 |
$12,006
688,159
kWh
|
$8,323
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
02 | 2.4224: Upgrade controls on compressors | $33,509 | $5,600 |
$19,764
1,133,060
kWh
|
$13,745
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
03 | 3.5311: Recover and reuse waste material | $16,330 | $15,000 | - | - | - |
$8,935
-
lb
|
$6,695
-
lb
|
- | - | - | - | $700 | |
04 | 2.7131: Add area lighting switches | $3,712 | $2,800 |
$3,712
213,072
kWh
|
- | - | - | - | - | - | - | - | - | |
05 | 2.3212: Optimize plant power factor | - | $57,200 | - | - | - | - | - | - | - | - | - | - | |
06 | 3.4111: Use closed cycle process to minimize waste water production | $48,539 | $3,154 |
$(-600.0)
(-31,360)
kWh
|
$(-98.0)
-
kW-mo/yr
|
$49,237
-
Tgal
|
- | - | - | - | - | - | - | |
07 | 4.611: Begin a practice of predictive / preventative maintenance | $89,264 | $5,400 | - | - | - | - | - | $(-1,536.0) | - | $82,800 | $8,000 | - | |
08 | 2.4131: Size electric motors for peak operating efficiency | $3,267 | $5,409 |
$1,847
106,096
kWh
|
$1,420
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
09 | 2.6218: Turn off equipment when not in use | $4,032 | $980 |
$3,647
209,261
kWh
|
$385
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
10 | 4.423: Move product using mechanical means | $27,522 | $71,000 | - | - | - | - | - | - | $27,522 | - | - | - | |
TOTAL RECOMMENDED | $246,504 | $181,543 |
$40,376
2,318,288
kWh
|
$23,775
-
kW-mo/yr
|
$49,237
-
Tgal
|
$8,935
-
lb
|
$6,695
-
lb
|
$(-1,536.0) | $27,522 | $82,800 | $8,000 | $700 | ||
TOTAL IMPLEMENTED | $194,253 | $118,389 |
$37,264
2,136,576
kWh
|
$23,873
-
kW-mo/yr
|
- |
$8,935
-
lb
|
$6,695
-
lb
|
$(-1,536.0) | $27,522 | $82,800 | $8,000 | $700 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs