| Assessment Year | 1998 |
|---|---|
| Principal Product | Detectors |
| NAICS |
n/a
|
| SIC | 3669: Communications Equipment, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 430 |
| Plant Area |
n/a
|
| Annual Production | 410,000
pieces
|
| Production Hrs. Annual | 5,000
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $115,107 | 3,218,933 |
kWh
|
$0.036 |
| Electricity Demand | $37,560 | 93,900 |
kW-mo/yr
|
$0.40 |
| Electricity Fees | $254 | - |
|
- |
| Natural Gas | $4,604 | 1,001 |
MMBtu
|
$4.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $137,028 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $75,515 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.1191: Change procedures / equipment / operating conditions | $59,850 | $437 | - | - |
$63,350
-
lb
|
- | - | $(-3,500.0) | - | |
| 02 | 4.321: Optimize production lot sizes and inventories | $53,400 | $18,750 | - | - | - | $57,000 | - | - | $(-3,600.0) | |
| 03 | 3.1161: Eliminate/reduce an operation | $627 | - | - | - | - | - | $627 | - | - | |
| 04 | 4.652: Replace existing equipment with more suitable substitutes | $6,605 | - | - | - | - | $4,025 | - | $2,580 | - | |
| 05 | 2.4224: Upgrade controls on compressors | $7,486 | $1,210 |
$6,483
183,763
kWh
|
$1,003
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $9,060 | $2,670 |
$4,624
131,008
kWh
|
$1,512
-
kW-mo/yr
|
- | $222 | - | - | $2,702 | |
| TOTAL RECOMMENDED | $137,028 | $23,067 |
$11,107
314,771
kWh
|
$2,515
-
kW-mo/yr
|
$63,350
-
lb
|
$61,247 | $627 | $(-920.0) | $(-898.0) | ||
| TOTAL IMPLEMENTED | $75,515 | $3,107 |
$4,624
131,008
kWh
|
$1,512
-
kW-mo/yr
|
$63,350
-
lb
|
$4,247 | - | $(-920.0) | $2,702 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs