Assessment Year | 1996 |
---|---|
Principal Product | maraschino cherries |
NAICS |
n/a
|
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $50 M to 100M |
# of Employees | 102 |
Plant Area |
120,000
ft2
|
Annual Production | 16,117,786
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $93,032 | 2,446,366 |
kWh
|
$0.038 |
Electricity Demand | $27,459 | 6,864 |
kW-mo/yr
|
$4.00 |
Electricity Fees | $4,860 | - |
|
- |
Natural Gas | $186,884 | 71,633 |
MMBtu
|
$2.61 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $79,689 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,221 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2163: Use minimum steam operating pressure | $1,474 | - | - | - | - |
$1,474
-
MMBtu
|
- | - | - | - | - | |
02 | 2.2122: Install / repair insulation on condensate lines | $715 | $1,566 | - | - | - |
$715
-
MMBtu
|
- | - | - | - | - | |
03 | 2.7145: Install skylights | $1,025 | $2,800 |
$399
10,844
kWh
|
$311
-
kW-mo/yr
|
- | - | - | - | $179 | $136 | - | |
04 | 2.3212: Optimize plant power factor | $1,521 | $5,500 | - | - | $1,521 | - | - | - | - | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $5,430 | $10,982 |
$3,915
106,096
kWh
|
$1,515
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,593 | $4,500 |
$1,270
34,291
kWh
|
$323
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
07 | 2.4226: Use / purchase optimum sized compressor | $5,032 | $29,713 |
$4,093
110,785
kWh
|
$939
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
08 | 2.4224: Upgrade controls on compressors | $6,893 | $10,803 |
$5,672
153,576
kWh
|
$1,221
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
09 | 3.7211: Modify material application methods | $6,750 | $350 | - | - | - | - | - |
$6,750
-
lb
|
- | - | - | |
10 | 3.7121: Improve handling practices | $44,620 | $47,924 | - | - | - | - | - | - | $44,620 | - | - | |
11 | 3.4151: Minimize water usage | $4,636 | $14,416 | - | - | - | - |
$3,591
-
Tgal
|
- | - | - |
$1,045
-
Tgal
|
|
TOTAL RECOMMENDED | $79,689 | $128,554 |
$15,349
415,592
kWh
|
$4,309
-
kW-mo/yr
|
$1,521 |
$2,189
-
MMBtu
|
$3,591
-
Tgal
|
$6,750
-
lb
|
$44,799 | $136 |
$1,045
-
Tgal
|
||
TOTAL IMPLEMENTED | $7,221 | $31,279 |
$4,093
110,785
kWh
|
$939
-
kW-mo/yr
|
- |
$2,189
-
MMBtu
|
- | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs