ITAC Assessment: OR0283
ITAC logo
ITAC Assessment: OR0283
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product maraschino cherries
NAICS
n/a
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $50
M
to 100
M
# of Employees 102
Plant Area 120,000
ft2
Annual Production 16,117,786
lb
Production Hrs. Annual 6,000
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $93,032 2,446,366
kWh
Electricity Demand $27,459 6,864
kW-mo/yr
Electricity Fees $4,860 -
Natural Gas $186,884 71,633
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $79,689 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,221

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.2163: Use minimum steam operating pressure $1,474 - - - - $1,474
-
MMBtu
- - - - -
02 2.2122: Install / repair insulation on condensate lines $715 $1,566 - - - $715
-
MMBtu
- - - - -
03 2.7145: Install skylights $1,025 $2,800 $399
10,844
kWh
$311
-
kW-mo/yr
- - - - $179 $136 -
04 2.3212: Optimize plant power factor $1,521 $5,500 - - $1,521 - - - - - -
05 2.4133: Use most efficient type of electric motors $5,430 $10,982 $3,915
106,096
kWh
$1,515
-
kW-mo/yr
- - - - - - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,593 $4,500 $1,270
34,291
kWh
$323
-
kW-mo/yr
- - - - - - -
07 2.4226: Use / purchase optimum sized compressor $5,032 $29,713 $4,093
110,785
kWh
$939
-
kW-mo/yr
- - - - - - -
08 2.4224: Upgrade controls on compressors $6,893 $10,803 $5,672
153,576
kWh
$1,221
-
kW-mo/yr
- - - - - - -
09 3.7211: Modify material application methods $6,750 $350 - - - - - $6,750
-
lb
- - -
10 3.7121: Improve handling practices $44,620 $47,924 - - - - - - $44,620 - -
11 3.4151: Minimize water usage $4,636 $14,416 - - - - $3,591
-
Tgal
- - - $1,045
-
Tgal
TOTAL RECOMMENDED $79,689 $128,554 $15,349
415,592
kWh
$4,309
-
kW-mo/yr
$1,521 $2,189
-
MMBtu
$3,591
-
Tgal
$6,750
-
lb
$44,799 $136 $1,045
-
Tgal
TOTAL IMPLEMENTED $7,221 $31,279 $4,093
110,785
kWh
$939
-
kW-mo/yr
- $2,189
-
MMBtu
- - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs