| Assessment Year | 1996 |
|---|---|
| Principal Product | air shafts and chucks |
| NAICS |
n/a
|
| SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
56,000
ft2
|
| Annual Production | 900,000
lb
|
| Production Hrs. Annual | 4,224
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $23,092 | 990,914 |
kWh
|
$0.023 |
| Electricity Demand | $7,613 | 3,360 |
kW-mo/yr
|
$2.27 |
| Natural Gas | $18,908 | 3,715 |
MMBtu
|
$5.09 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,997 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,203 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2515: Use optimum thickness insulation | $12,794 | $20,784 | - | - |
$12,794
-
MMBtu
|
- | - | |
| 02 | 3.3133: Use other waste concentration methods | $5,324 | $10,000 | - | - | - |
$6,124
-
gal
|
$(-800.0) | |
| 03 | 2.4224: Upgrade controls on compressors | $952 | $3,840 |
$485
25,205
kWh
|
$467
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $927 | $4,907 |
$501
26,084
kWh
|
$426
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $19,997 | $39,531 |
$986
51,289
kWh
|
$893
-
kW-mo/yr
|
$12,794
-
MMBtu
|
$6,124
-
gal
|
$(-800.0) | ||
| TOTAL IMPLEMENTED | $7,203 | $18,747 |
$986
51,289
kWh
|
$893
-
kW-mo/yr
|
- |
$6,124
-
gal
|
$(-800.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs