ITAC Assessment: OR0272
ITAC logo
ITAC Assessment: OR0272
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product apple juice concentrate
NAICS
n/a
SIC 2037: Frozen Fruits, Fruit Juices, and Vegetables
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 41,500
ft2
Annual Production 69,772,000
lb
Production Hrs. Annual 7,200
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $153,568 6,148,300
kWh
Electricity Demand $101,723 17,796
kW-mo/yr
Natural Gas $278,738 72,501
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $271,838 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $247,976

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Water Consumption Savings
01 3.4114: Replace city water with recycled water via cooling tower $11,768 $11,600 $(-1,041.0)
(-47,186)
kWh
$(-1,051.0)
-
kW-mo/yr
- - $13,860
-
Tgal
02 3.6193: Install equipment (eg compactor) to reduce disposal costs $247,053 $1,000,000 $(-13,135.0)
(-594,666)
kWh
$(-4,794.0)
-
kW-mo/yr
- $264,982
-
lb
-
03 2.1232: Keep boiler tubes clean $1,014 $1,000 - - $1,014
-
MMBtu
- -
04 2.4133: Use most efficient type of electric motors $923 $2,220 $577
4,396
kWh
$346
-
kW-mo/yr
- - -
05 2.6232: Install set-back timers $11,080 $105,000 $9,810
444,314
kWh
$1,270
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $271,838 $1,119,820 $(-3,789.0)
(-193,142)
kWh
$(-4,229.0)
-
kW-mo/yr
$1,014
-
MMBtu
$264,982
-
lb
$13,860
-
Tgal
TOTAL IMPLEMENTED $247,976 $1,002,220 $(-12,558.0)
(-590,270)
kWh
$(-4,448.0)
-
kW-mo/yr
- $264,982
-
lb
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs